(a) When required. Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical, or plumbing system, the installation of which is regulated by the technical codes, or to cause any such work to be done, shall first make application to the building official and obtain the required permit for the work. (b) Time required. Permits are to be obtained at least eight hours before the beginning of any construction, except that in the event of emergency, permits must be obtained within 24 hours of the next business day following the emergency. In the event of emergency, fees for permit issuance shall apply unless specifically waived by the building department or the sole commissioner. (c) Exceptions. Permits shall not be required for the following mechanical work: (1) Any portable heating appliance; (2) Any portable ventilation equipment; (3) Any portable cooling unit; (4) Any steam, hot or chilled water piping within any heating or cooling equipment regulated by this chapter; (5) Replacement of any part which does not alter its approval or make it unsafe; (6) Any portable evaporative cooler; (7) Any self-contained refrigeration system containing ten pounds (4.54 kg) or less of refrigerant and actuated by motors of one horsepower (746 W) or less; (8) Demolition of a structure; (9) Repairs completed by an owner on his own home; (10) Work on building not intended for human habitation; (11) Construction of driveways, including paving; (12) Installation of satellite communications equipment; and (13) Such other repairs as may be deemed exempt by the building department or the sole commissioner. (d) Work authorized. A building, electrical, gas, mechanical or plumbing permit shall carry with it the right to construct or install the work, provided the same are shown on the drawings and set forth in the specifications filed with the application for the permit. Where these are not shown on the drawings and covered by the specifications submitted with the application, separate permits shall be required. (e) Minor repairs. Ordinary minor repairs may be made with the approval of the building official without a permit, provided that such repairs shall not violate any of the provisions of the technical codes. (f) Information required. Each application for a permit, with the required fee, shall be filed with the building official on a form furnished for that purpose, and shall contain a general description of the proposed work and its location. The application shall be signed by the owner or his authorized agent. The building permit application shall indicate the proposed occupancy of all parts of the building and of that portion of the site or lot, if any, not covered by the building or structure, and shall contain such other information as may be required by the building official. (g) Time limitations. An application for a permit for any proposed work shall be deemed to have been abandoned six months after the date of filing for the permit, unless before then a permit has been issued. One or more extensions of time for periods of not more than 90 days each may be allowed by the building official for the application, provided that the extension is requested in writing and justifiable cause is demonstrated.