Part II - CODE OF ORDINANCES / Chapter 14 - BUILDINGS AND BUILDING REGULATIONS / Article IV - PERMITS

Sec. 14-81. Inspections.

About this text

  • As published by Municode, current through 2023-08-17
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Existing building inspections. Before issuing a permit, the building official may examine or cause to be examined any building or electrical, gas, mechanical or plumbing system for which an application has been received for a permit to enlarge, alter, repair, move, demolish, install, or change the occupancy. He shall inspect all buildings, structures, and electrical, gas, mechanical and plumbing systems, from time to time, during and upon completion of the work for which a permit was issued. He shall make a record of every such examination and inspection and of all violations of the technical codes.

(b) Manufacturers and fabricators. When deemed necessary by the building official, he shall make or cause to be made an inspection of materials or assemblies at the point of manufacture or fabrication. A record shall be made of every such examination and inspection and of all violations of the technical codes.

(c) Inspection service. The building official may make or cause to be made the inspections required in this article. He may accept reports of inspectors of recognized inspection services, provided that after investigation he is satisfied as to their qualifications and reliability. A certificate called for by any provision of the technical codes shall not be based on such reports unless the same are in writing and certified by a responsible officer of such service.

(d) Inspection prior to certificate of occupancy or completion. The building official shall inspect or cause to be inspected at various intervals all construction or work for which a permit is required, and a final inspection shall be made of every building, structure, or electrical, gas, mechanical or plumbing system upon completion, prior to the issuance of the certificate of occupancy or completion.

(e) Posting of permit. Work requiring a permit shall not commence until the permit holder or his agent posts the permit card in a conspicuous place on the premises. The permit shall be protected from the weather and located in such a position as to permit the building official or representative to conveniently make the required entries thereon. The permit card shall be maintained in such position by the permit holder until the certificate of occupancy or completion is issued by the building official.

(f) Required inspections. The building official, upon notification from the permit holder or his agent, shall make the following inspections and such other inspections as necessary, and shall either release that portion of the construction or shall notify the permit holder or his agent of any violations which must be corrected in order to comply with the technical codes:

(1) Building.

a. Foundation inspection, to be made after trenches are excavated and forms erected.

b. Frame inspection, to be made after the roof, all framing, fire blocking and bracing are in place, and all concealing wiring, all pipes, chimneys, ducts and vents are complete.

c. Final inspection, to be made after the building is completed and ready for occupancy.

(2) Electrical.

a. Underground inspection, to be made after trenches or ditches are excavated, conduit or cable installed, and before any backfill is put in place.

b. Rough-in inspection, to be made after the roof, framing, fire blocking and bracing is in place and prior to the installation of wall or ceiling membranes.

c. Final inspection, to be made after the building is complete, all required electrical fixtures are in place and properly connected or protected, and the structure is ready for occupancy.

(3) Plumbing.

a. Underground inspection, to be made after trenches or ditches are excavated, piping installed, and before any backfill is put in place.

b. Rough-in inspection, to be made after the roof, framing, fire blocking and bracing is in place and all soil, waste and vent piping is complete, and prior to the installation of wall or ceiling membranes.

c. Final inspection, to be made after the building is complete, all plumbing fixtures are in place and properly connected, and the structure is ready for occupancy.

(4) Mechanical.

a. Underground inspection, to be made after trenches or ditches are excavated, underground duct and fuel piping installed, and before any backfill is put in place.

b. Rough-in inspection, to be made after the roof, framing, fire blocking and bracing are in place and all ducting, and other concealed components are complete, and prior to the installation of wall or ceiling membranes.

c. Final inspection, to be made after the building is complete, the mechanical system is in place and properly connected, and the structure is ready for occupancy.

(5) Gas.

a. Rough piping inspection, to be made after all new piping authorized by the permit has been installed, and before any such piping has been covered or concealed or any fixtures or gas appliances have been connected.

b. Final piping inspection, to be made after all piping authorized by the permit has been installed and after all portions which are to be concealed by plastering or otherwise have been so concealed, and before any fixtures or gas appliances have been connected. This inspection shall include a pressure test.

c. Final inspection, to be made on all new gas work authorized by the permit and such portions of existing systems as may be affected by new work or any changes, to ensure compliance with all the requirements of this chapter and to ensure that the installation and construction of the gas system is in accordance with reviewed plans.

(6) Energy.

a. Slab insulation inspection, to be made when the slab rough inspection is made.

This is to ensure that all slab perimeter insulation is installed correctly.

b. Rough-in inspection, which verifies that all perimeter wall insulation is installed correctly before it is concealed by wallboard. The structure shall be checked to ensure that all openings that will allow air infiltration are sealed by approved methods.

c. Final inspection, which verifies that all ceiling, crawl space, or basement insulation is installed in compliance with the technical codes. The SEER rating on the air conditioning unit shall be checked for compliance.

(g) Written release. Work shall not be done on any part of a building, structure, or electrical, gas, mechanical or plumbing system beyond the point indicated in each successive inspection without first obtaining a written release from the building official. Such written release shall be given only after an inspection has been made of each successive step in the construction or installation as indicated by each of the three inspections listed in subsections (f)(1)—(6) of this section.

(h) Reinforcing steel and structural frames. Reinforcing steel or structural framework of any part of any building or structure shall not be covered or concealed without first obtaining a release from the building official.

(i) Plaster fire protection. In all buildings where plaster is used for fire protection purposes, the permit holder or his agent shall notify the building official after all lathing and backing is in place. Plaster shall not be applied until the release from the building official has been received.

(j) Waiver of inspection. In the event of natural disaster, building inspection shall be waived during the period of the disaster, as declared and defined by the sole commissioner.

History

The history line the source prints at the end of the section.

(Res. of 6-20-1986(1), § 3.8)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:bleckley-county/code/14-81@2023-08-17-df47e5d53f

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Bleckley County Code of Ordinances, Sec. 14-81. Inspections | Georgia Commons