B-1-11.1. Prior approval.
No construction or land disturbing activity of any kind, including grading, installation of improvements, or building shall begin on any land subject to these regulations without prior approval and implementation of the preliminary plat and soil erosion and sedimentation control plan where required by local, state or federal laws or regulations.
B-1-11.2. Grading and land-disturbing activity.
Where applicable, grading and land-disturbing operations may commence once approval of the preliminary plat and issuance of the land disturbing activity permit are granted. Soil erosion and sedimentation control measures prescribed in the soil erosion and sedimentation control plan must be installed prior to any land-disturbing or grading activity where applicable.
B-1-11.3. Utilities.
Utility installation shall not occur until the county engineer has approved the rough grade of the street and shoulder preparation.
B-1-11.4. Inspections.
Periodic inspection during the installation of the required improvements in a subdivision shall be made by the building and zoning official and county engineer to insure conformity with the approved plans and specifications. The subdivider shall notify the building and zoning official when each phase of the installation is completed and ready for inspection.
B-1-11.5. Sale and transfer.
No lot or parcel of land shall be sold or transferred or a building permit issued until the final plat, of which said lot or parcel is a part, shall have been approved and recorded as provided for in these regulations.
B-1-11.6. Construction standards.
A building or structure shall be considered substandard if or when it does not meet the requirements of the Uniform Building Code of Georgia, or any other code or ordinance adopted by the county or its governing authority.
B-1-11.7. Building permits.
The building official shall not issue any permit for the construction of any building or structure to be located in any subdivision or planned development until the required plat has been approved and recorded as provided for in these regulations.
B-1-11.8. Occupancy.
Within each phase of development, no building may be occupied for dwelling or other purposes nor shall an occupancy permit be issued for any building until all roads and required utility installations, including water supply and sanitary sewer systems, have been completed to the satisfaction of the building official.