(a) Permit application; when required. Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical, or plumbing system, the installation of which is regulated by the construction codes, or to cause any such work to be done, shall first make application to the building official and obtain the required permit for the work.

(b) Work exempt from permit. Exemptions from permit requirements of this division shall not be deemed to grant authorization for any work to be done in any manner in violation of the provisions of this code or any other laws or ordinances of this jurisdiction. Permits shall not be required for the following:

(1) Building:

a. One-story detached accessory structures used as tool and storage sheds, playhouses and similar uses, provided the floor area does not exceed 200 square feet (11.15 m2

).

b. Fences not over six feet (1,829 mm) high.

c. Oil derricks.

d. Retaining walls which are not over four feet (1,219 mm) in height measured from the bottom of the footing to the top of the wall, unless supporting a surcharge or impounding Class I, II or III-A liquids.

e. Water tanks supported directly upon grade if the capacity does not exceed 5,000 gallons (18,927 L) and the ratio of height to diameter or width does not exceed two to one.

f. Sidewalks and driveways not more than 30 inches (762 mm) above grade and not over any basement or story below and which are not part of an accessible route.

g. Painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work.

h. Temporary motion picture, television and theater stage sets and scenery.

i. Prefabricated swimming pools accessory to a group R-3 occupancy, which are less than 24 inches (610 mm) deep, do not exceed 5,000 gallons (19,000 L) and are installed entirely above ground.

j. Shade cloth structures constructed for nursery or agricultural purposes and not including service systems.

k. Swings and other playground equipment accessory to one- and two-family dwellings.

l. Window awnings supported by an exterior wall of group R-3 and group U occupancies.

m. Movable cases, counters and partitions not over five feet nine inches (1,753 mm) in height.

(2) Electrical:

a. Repairs and maintenance: Minor repair work, including the replacement of lamps or the connection of approved portable electrical equipment to approved permanently installed receptacles.

b. Radio and television transmitting stations: The provisions of this code shall not apply to electrical equipment used for radio and television transmissions, but do apply to equipment and wiring for power supply, the installations of towers and antennas.

c. Temporary testing systems: A permit shall not be required for the installation of any temporary system required for the testing or servicing of electrical equipment or apparatus.

(3) Gas:

a. Portable heating appliance.

b. Replacement of any minor part that does not alter approval of equipment or make such equipment unsafe.

(4) Mechanical:

a. Portable heating appliance;

b. Portable ventilation equipment;

c. Portable cooling unit;

d. Steam, hot or chilled water piping within any heating or cooling equipment regulated by this code;

e. Replacement of any part which does not alter its approval or make it unsafe;

f. Portable evaporative cooler;

g. Self-contained refrigeration system containing ten pounds (4.54 kg) or less of refrigerant and actuated by motors of one horsepower (746 W) or less.

(5) Plumbing:

a. The stopping of leaks in drains, water, soil, waste or vent pipe; provided, however, that if any concealed trap, drainpipe, water, soil, waste or vent pipe becomes defective and it becomes necessary to remove and replace the same with new material, such work shall be considered as new work and a permit shall be obtained and inspection made as provided in this code.

b. The clearing of stoppages or the repairing of leaks in pipes, valves or fixtures, and the removal and reinstallation of water closets, provided such repairs do not involve or require the replacement or rearrangement of valves, pipes or fixtures.

(6) Emergency repairs. Where equipment replacements and repairs must be performed in an emergency situation, the permit application shall be submitted within the next working business day to the building official.

(7) Repairs. Application or notice to the building official is not required for ordinary repairs to structures. Such repairs shall not include the cutting away of any wall, partition or portion thereof, the removal or cutting of any structural beam or load bearing support, or the removal or change of any required means of egress, or rearrangement of parts of a structure affecting the egress requirements; nor shall ordinary repairs include addition to, alteration of, replacement or relocation of any standpipe, water supply, sewer, drainage, drain leader, gas, soil, waste, vent or similar piping, electric wiring or mechanical or other work affecting public health or general safety.

(8) Public service agencies. A permit shall not be required for the installation, alteration or repair of generation, transmission, distribution or metering or other related equipment that is under the ownership and control of public service agencies by established right.

(9) Minor repairs. Ordinary minor repairs may be made with the approval of the building official without a permit, provided that such repairs shall not violate any of the provisions of the construction codes.

(c) Work authorized. A permit required by this division shall carry with it the right to construct or install the work, provided the same are shown on the drawings and set forth in the specifications filed with the application for the permit. Where these are not shown on the drawings and covered by the specifications submitted with the application, separate permits shall be required.

(1) Information required. Each application for a permit shall be filed with the building official on a form furnished for that purpose, and shall contain a general description of the proposed work and its location. The owner or his/her authorized agent shall sign the application. The building permit application shall indicate the proposed occupancy of all parts of the building and of that portion of the site or lot, if any, not covered by the building or structure, and shall contain such other information as may be required by the building official.

(2) Time limitations. An application for a permit for any proposed work shall be deemed to have been abandoned six months after the date of filing for the permit, unless a permit has been issued. One or more extensions of time for periods of not more than 90 days each may be allowed by the building official for the application, provided the extension is requested in writing and justifiable cause is demonstrated.

(d) Drawings and specifications.

(1) Requirements. When required by the building official, two or more copies of specifications, and of drawings drawn to scale with sufficient clarity and detail to indicate the nature and character of the work, shall accompany the application for a permit. Such drawings and specifications shall contain information, in the form of notes or otherwise, as to the quality of materials, where quality is essential to conformity with the construction codes. Such information shall be specific, and the construction codes shall not be cited as a whole or in part, nor shall the term "legal" or its equivalent be used, as a substitute for specific information. All information, drawings, specifications and accompanying data shall bear the name and signature of the person responsible for the design.

(2) Additional data. The building official may require details, computations, stress diagrams, and other data necessary to describe the construction or installation and the basis of calculations. All drawings, specifications and accompanying data required by the building official to be prepared by a design professional shall be affixed with their official seal.

(3) Design professional. The design professional shall be an architect or engineer legally registered under the laws of this state regulating the practice of architecture or engineering and shall affix his/her official seal to said drawings, specifications and accompanying data, for the following:

a. All group assembly (A), educational (E), and institutional (I) occupancies;

b. Buildings and structures three stories or more high; or

c. Buildings and structures 5,000 sq. ft. (465 m2 ) or more in area.

For all other buildings and structures, the submittal shall bear the certification of the applicant that some specific state law exception permits its preparation by a person not so registered.

(4) Exception: Single-family dwellings, regardless of size, shall require neither a registered architect nor engineer, nor a certification that an architect or engineer is not required.

(5) Structural and fire resistance integrity. Plans for all buildings shall indicate how required structural and fire resistance integrity will be maintained where a penetration of a required fire resistance wall, floor or partition will be made for electrical, gas, mechanical, plumbing, signal and communication conduits, pipes and systems and also indicate in sufficient detail how the fire integrity will be maintained where required fire resistance floors intersect the exterior walls.

(6) Site drawings. Drawings shall show the location of the proposed building or structure and of every existing building or structure on the site or lot. The building official may require a boundary line survey prepared by a qualified surveyor.

(7) Hazardous occupancies. The building official may require the following:

a. General site plan. A general site plan drawn at a legible scale which shall include, but not be limited to, the location of all buildings, exterior storage facilities, permanent access ways, evacuation routes, parking lots, internal roads, chemical loading areas, equipment cleaning areas, storm and sanitary sewer accesses, emergency equipment and adjacent property uses. The exterior storage areas shall be identified with the hazard classes and the maximum quantities per hazard class of hazardous materials stored.

b. Building floor plan. A building floor plan drawn to a legible scale which shall include, but not be limited to, all hazardous materials storage facilities within the building and shall indicate rooms, doorways, corridors, exits, fire rated assemblies with their hourly rating, location of liquid tight rooms, and evacuation routes. Each hazardous materials storage facility shall be identified on the plan with the hazard classes and quantity range per hazard class or the hazardous materials stored.

(e) Examination of documents.

(1) Plan review. The building official shall examine or cause to be examined each application for a permit and the accompanying documents, consisting of drawings, specifications, computations, and additional data, and shall ascertain by such examinations whether the construction indicted and described is in accordance with the requirements of the construction codes and all other pertinent laws or ordinances. Any documents requiring review by the local fire department and/or state fire marshall's office will be forwarded to their respective offices by the building official for examination. A permit shall not be issued for work requiring local and/or state fire approval until such has been made in writing to the building official.

(2) Affidavits. The building official may accept a sworn affidavit from a registered architect or engineer stating that the plans submitted conform to the construction codes. For buildings and structures the affidavit shall state that the plans conform to the laws as to egress, type of construction and general arrangement and if accompanied by drawings showing the structural design, and by a statement that the plans and design conform to the requirements of the construction codes as to strength, stresses, strains, loads and stability. The building official may without any examination or inspection accept such affidavit, provided the architect or engineer who made such affidavit agrees to submit to the building official, copies of inspection reports as inspections are performed and upon completion of the structure, electrical, gas, mechanical or plumbing systems a certification that the structure, electrical, gas, mechanical or plumbing system has been erected in accordance with the requirements of the construction codes. Where the building official relies upon such affidavit, the architect or engineer shall assume full responsibility for the compliance with all provisions of the construction codes and other pertinent laws or ordinances.

(f) Issuing permits.

(1) Action on permits. The building official shall act upon an application for a permit without unreasonable or unnecessary delay. If the building official is satisfied that the work described in an application for a permit and the contract documents filed therewith conform to the requirements of the construction codes and other pertinent laws and ordinances, he shall issue a permit to the applicant.

(2) Refusal to issue permit. If the application for a permit and the accompanying contract documents describing the work do not conform to the requirements of the construction codes or other pertinent laws or ordinances, the building official shall not issue a permit, but shall return the contract documents to the applicant with his refusal to issue such permit. Such refusal shall, when requested, be in writing and shall contain the reason for refusal.

(3) Public right-of-way. No construction of any structure (temporary or permanent), building, or alteration thereof shall be undertaken where said building change will affect the exterior walls, bays, balconies, or other appendages to project onto any street, alley or public right-of-way, unless the applicant has made application and been granted approval by proper authority to alter the lines of the public street on which the building, erection or alteration shall project; and it shall be the duty of the building official to see that the public right-of-way is not encroached upon.

(g) Contractors responsibilities. It shall be the duty of every person who shall make contracts for the installation or repairs of building, structure, electrical, gas, mechanical, sprinkler or plumbing systems, for which a permit is required, to comply with state or county ordinances, rules and regulations concerning licensing. In such case that the state requires a contractor to have obtained a state license before they are permitted to perform work, the contractor shall supply the department with their license number before receiving a permit for work to be performed.

(h) Conditions of the permit.

(1) Permit intent. A permit issued shall be construed to be a license to proceed with the work and not as authority to violate, cancel, alter, or set aside any of the provisions of the construction codes, or other applicable law or ordinances, nor shall issuance of a permit prevent the building official from thereafter requiring a correction of errors in plans, construction, or violations of the construction codes. Every permit issued shall become invalid unless the work authorized by such permit is commenced within six months after its issuance, or if the work authorized by such permit is suspended or abandoned for a period of six months after the time the worked is commenced. One or more extensions of time, for periods not more than 90 days each, may be allowed for the permit. The extension shall be requested in writing and justifiable cause demonstrated. Extensions shall be in writing by the building official.

(2) Permit issued on basis of a certificate of a design professional. Whenever a permit is issued in reliance upon a certificate of a design professional or whenever the work to be covered by a permit involves installation under conditions which, in the opinion of the building official, are hazardous or complex, the building official shall require that the design professional who signed the certificate or prepared the drawings or computations shall supervise such work. In addition, they shall be responsible for conformity with the permit, provide copies of inspection reports as inspections are performed, and upon completion make and file with the building official a certificate that the work has been done in conformity with the reviewed plans and with the structural provisions of the construction codes. In the event such architect or engineer is not available, the owner shall employ in his stead a competent person or agency whose qualifications are reviewed by the building official.

(3) Plans. When the building official issues a permit, he/she shall enforce, in writing or by stamp on all sets of plans or drawings that such plans or drawings have been reviewed and indicate that such plans or drawings have been approved or denied. The building official shall retain one set and the remaining sets shall be returned to the applicant.

A copy of the approved plans or drawings shall be kept on the site of construction or work at all times and shall be made available for review when requested by the building official or designee.

(i) Fees.

(1) Prescribed fees. A permit shall not be issued until the fees prescribed by the board of commissioners have been paid. Nor shall an amendment to a permit be released until the additional fee, if any, due to an increase in the estimated cost of the building, structure, electrical, plumbing, mechanical or gas systems, etc. has been paid.

(2) Work commencing before permit issuance. Any person who commences any work on a building, structure, electrical, gas, mechanical, or plumbing, including installation or relocation of a manufactured home or conventional home before obtaining the necessary permits, shall be subject to a penalty of 100 percent of the usual permit fee in addition to the required permit fees.

(3) Accounting. The building official shall keep a permanent and accurate accounting of all permit fees and other money collected, the names of all persons upon whose account the same was paid, along with the date and amount thereof.

(4) Schedule of permit fees ICC International Residential Code for One and Two-Family Dwellings and IBC International Building Code. On all buildings, structures, electrical, plumbing, mechanical and gas systems or alterations requiring a permit, a fee for each permit shall be paid as required, in accordance with the fee schedules as set by the governing body.

(5) Building permit valuations for construction projects that are classified as new construction, the number of square feet of construction or the number of square feet of construction to be served by the system to be installed, in conjunction with and limited by the building valuation data, as established from time to time by the International Code Council or by similar data, and in conjunction with and limited by the hourly rate, O.C.G.A. § 48-13-9. For construction projects that are classified as renovation and all other construction projects other than those classified as new construction, the cost of the project in conjunction with and limited by the building valuation data that conforms with the principles and methods established from time to time by the International Code Council or by similar data, and in conjunction with and limited by the hourly rate, O.C.G.A. § 48-13-9. If, in the opinion of the building official, the valuation of building, alteration, structure, electrical, gas, mechanical or plumbing systems appears to be underestimated on the application, permit shall be denied, unless the applicant can show detailed estimates to meet the approval of the building official. Permit valuations shall include total cost, such as electrical, gas, mechanical, plumbing equipment and other systems, including materials and labor.

(6) Reinspection fees. Reinspection fees shall be required when work performed is required to be reinspected due to the following reasons:

a. The required permits are not posted on the job site.

b. The required construction drive and/or erosion control measures are not installed.

c. The work is not ready for inspection when an inspection is requested and performed.

d. Work to be inspected has been covered and proper inspection cannot be performed.

e. A reinspection has been requested without correction of previously noted violations or deficiencies.

Reinspection fees shall be set by the board of commissioners as part of the schedule of fees, except that fee may be doubled for repeated failure to correct violations. Fees charged shall be paid at the office of the building official before further inspections are performed.

History

The history line the source prints at the end of the section.

(Res./Ord. of 6-3-03, § 2; Ord. of 6-2-15, § 1)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:carroll-county/code/18-15@2025-05-06-e9447451ce

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Carroll County Code of Ordinances, Sec. 18-15. Permits | Georgia Commons