If, on or before the 11th day as described in 2(b), an application is deemed complete, the county shall approve or deny an application within ten calendar days unless a joint meeting between the applicant and Carroll County is deemed as necessary. (1) If a joint meeting is deemed necessary, the joint meeting must occur within 15 calendars days of notification of completion and the joint meeting shall include: a. Where applicant is going to conduct work; b. When the work will be conducted; c. What type of work will be done; d. Who Carroll County can contact for specific details or related questions; and e. Any permit seeking approval under application. f. Following a joint meeting between the applicant and Carroll County, the County shall deny or approve the application within ten calendar days. (2) Upon final approval, any required permit permitted shall be deemed issued.