Sec. 86-171. Site grading—General requirements.

About this text

  • As published by Municode, current through 2025-05-06
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

All design, construction, and installation of streets and stormwater conveyance facilities are subject to the standards of the public works department and approval of the public works department.

(1) Grading shall be done in accordance with the lines and grades shown on the approved construction plans.

(2) Embankments shall be placed in uniform layers not to exceed a compacted thickness of six inches per layer and shall be compacted to a density of 95 percent in all areas where structures, parking lots and drives, streets, and utilities are to be placed. All other embankments are to be compacted to at least 85 percent.

(3) The maximum slopes for cut or fill shall be 2:1 (two feet of horizontal run for each foot of rise or fall). The depth of cut referred to herein shall be the maximum cut or fill occurring in any one section of cut or fill. The slope of cut or fill shall be uniform throughout for each section of cut or fill except when the engineer approves benching.

When a cut is made in rock that requires blasting, the slope may be steeper if pre-splitting is employed and upon submission of a geotechnical report which substantiates the integrity of the rock in the steeper condition, subject to the review and approval of the engineer.

(4) While most soils in the area can be safely stabilized at a 2:1 slope, some soils exhibit a low shearing resistance and a low cohesiveness. These soils typically are micaceous silts and sandy soils with little or no clay. If the 2:1 slope shows evidence of shearing, non-cohesiveness, sliding, or inability to maintain compaction, the slope shall be stabilized at 3:1 or by using such mechanical methods as needed (such as retaining walls or "grow mats" stapled in place) to maintain slope, height and integrity.

History

The history line the source prints at the end of the section.

(Ord. of 10-16-01, § 1; Ord. of 1-6-15, § 1)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:carroll-county/code/86-171@2025-05-06-c30be54115

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.