Charlton County · Code of Ordinances
Part II - CODE OF ORDINANCES / Part A - GENERAL CODE OF ORDINANCES / Chapter 110 - BUILDINGS AND BUILDING REGULATIONS / Article V - SOLAR FARMS
Sec. 110-234. Application for permit, fee, and revocation of permit.
About this text
- As published by Municode, current through 2023-05-18
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Before commencing operations, all solar farms shall submit an application for a solar farm permit on the form prescribed by the county code enforcement department and provide proof of compliance with all standards for solar farms outlined in this article. No solar farm shall commence operations until it has been inspected by the county code enforcement department and obtained the permit required by this section.
(b) An application for a solar farm permit shall be accompanied by a comprehensive site plan for the solar farm, which shall include, but not be limited to:
(1) Drawings prepared by a professional engineer licensed to practice in Georgia that clearly illustrate the design of the solar farm;
(2) A project summary;
(3) General procedures for operation and maintenance of the installation;
(4) Measures for maintaining safe access to the installation;
(5) Electrical schematics;
(6) Soil erosion and sediment control;
(7) Landscape plans;
(8) Temporary or permanent roads or driveways;
(9) Grading;
(10) Vegetation clearing and planting and mitigation or screening with vegetation, structures, or fences;
(11) Exterior lighting and any screening.
(c) The applicant shall provide additional copies of the comprehensive site plan to the county sheriff's office, fire department, and emergency management agency. The comprehensive site plan must be approved in writing by the county code enforcement department before a solar farm may receive a permit or commence operations.
(d) At the time of application, each applicant shall pay a non-refundable permit fee in the amount established by the county code enforcement department.
(e) A permit may be revoked by the county code enforcement department for any solar farm which is not in full compliance with this article. Prior to revoking the permit, the county code enforcement department shall provide three calendar days' written notice of any deficiencies to the solar farm owner or operator via U.S. Mail, overnight delivery, or hand delivery. If the deficiencies are not corrected within those three days, or in the event a remedy is not feasible within this three-day time period and the permit holder does not submit a reasonable cure plan within the three-day period, the county code enforcement department may revoke the solar farm's permit and require the solar farm to submit a new application before recommencing operations. During the time that a solar farm permit is revoked, the solar farm shall post a sign at each entrance to the solar farm no smaller than one foot by two feet stating: "This solar farm's operations have ceased due to noncompliance with the Charlton County Code of Ordinances. For more information, contact the Charlton County Code Enforcement Department."
History
(Ord. No. 16 of 2018)