Sec. 2-174. Fiscal responsibility.

About this text

  • As published by Municode, current through 2026-01-20
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Every change order in excess of $25,000.00 under a public works construction contract with the county shall be subject to prior approval by the board of commissioners after receiving a report from the county manager as to the effect of the change order on the total project budget or the total contract budget. The county manager is authorized to execute all other change orders.

History

The history line the source prints at the end of the section.

(Ord. of 4-19-16(1), § 2-5-6.04; Ord. No. 2022-O-004, § 2-5-6.04, 2-1-22; Ord. of 09-19- 2023(1))

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:cherokee-county/code/2-174@2026-01-20-c6828f143f

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.