For construction activity, exceptions to the time restrictions set forth in section 26-40(a)(7) can be approved administratively by the chief building official (CBO) with an after-hours permit. A written request for an after-hours permit must be submitted to the CBO, indicating the dates and times requested, subject to the following requirements: (1) The applicant must detail the work to be completed after-hours and provide any supporting documentation, as determined by the CBO. (2) The applicant must demonstrate that being restricted to the hours set forth in section 26-40(a)(7) would cause a hardship. (3) The applicant must demonstrate that the dates and hours needed to complete the construction activity after-hours are minimized to the greatest extent possible and would not have an adverse effect on community health, safety, or welfare. (4) Upon approval of an after-hours permit, the CBO is directed to notify the county manager, chief marshal, community development agency director, planning and zoning director, communications director, and the county commissioner representing the district where the construction work is occurring. (5) If there is deviation from the dates and times permitted, the applicant must re-submit the request. (6) A decision of the CBO is appealable to the board of commissioners in accordance with section 26-42.