Sec. 110-26. Procedure for plat approval for subdivisions.

About this text

  • As published by Municode, current through 2025-11-20
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Any owner of land lying within the area of jurisdiction of these subdivision regulations wishing to divide such land into two or more lots, sites or divisions for the purpose, either immediate or future, of sale or building development, or wishing to resubdivide for this purpose, shall submit a plan of such proposed subdivision to the subdivision administrator and, if using septic tanks, to the county health department for its consideration. The following requirements shall govern the procedure for plat approval for subdivisions:

(1) Prepare a complete set of construction plans which shall include at a minimum:

a. Preliminary site plan.

b. Site grading plans.

c. Roadway development plans (see Cobb County Development Standards).

d. Stormwater management plan (see Cobb County Development Standards).

e. Fire safety standards (see chapter 54, article III).

f. Water and sanitary sewer plans (see Cobb County Development Standards).

g. Erosion and sediment control plans (see section 50-75).

h. Tree protection and replacement plan (see Cobb County Development Standards).

i. Additional site-specific information as may be necessary.

(2) Submit two sets of the construction plans, to the subdivision administrator for consideration by the Development Review Committee. The action and/or recommendations shall be noted on the plans and returned to the submitter.

Upon resubmittal of revised plans, and verification that all staff comments have been properly addressed, the project will be made eligible for permitting Upon receiving construction plan approval as outlined in section 102.03 of the Cobb County Development Standards, a land disturbance permit shall be issued.

(3) Upon completion of site grading, paving, utility and infrastructure installation, prepare a final plat (see section 110-30). No building permits shall be issued before approval of the final plat.

(4) Submit final plat for health department approval if septic tanks are to be used for sewerage disposal.

(5) Submit final plat and the platting fee to the subdivision administrator for approval on the basis of the approved construction plans.

Note: Approval of the final plat does not constitute final acceptance of the improvements.

(6) The applicant shall have the final plat recorded after the necessary signatures have been placed upon it.

(7) The subdivider may begin to sell lots.

(8) Ensure that all inspections have been made at proper phases of road construction, so that the one-year maintenance period may begin promptly.

(9) Any required conservation easements and/or mandatory covenants protecting open space and/or conservation areas shall be recorded and verification of such recording provided to Community Development prior to approval of the final plat.

History

The history line the source prints at the end of the section.

(Ord. of 9-24-74, art. VI; Ord. of 2-22-77; Ord. of 4-26-77; Ord. of 1-24-06; Amd. of 2-9-21; Amd. of 11-21-24)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:cobb-county/code/110-26@2025-11-20-7435739d8e

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.