Sec. 122-314. Billing, payments, delinquencies, and adjustments.

About this text

  • As published by Municode, current through 2025-11-20
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Water and/or sewer account holders. Stormwater services fees shall be billed monthly. Stormwater service fees shall be included on the parcel's monthly

water and/or sewer bill. The water and/or sewer account holder is responsible for the stormwater service fees even if the account holder is not the property owner.

(b) Customers without a water and/or sewer account.

The owner(s) of parcels not billed by the county water system for water and/or sewer shall receive a stormwater service fee only bill, which may be billed monthly, bi-monthly, or quarterly. When no homeowners' association parcels are billed by the county water system for water and/or sewer, the impervious area for

any such parcel owned by such homeowners' association may be allocated among all parcels served by the impervious area (e.g., private drives, parking spaces,

etc.).

(c) Underbilling or failure to receive bill. The bill may be sent through the United States mail or by alternative means notifying the customer of the amount of the bill and the date the payment is due. Failure to receive a bill is not justification for nonpayment.

Regardless of the party to whom the bill is initially directed, the owner of each parcel of developed land shall be ultimately obligated to pay such fee. If a customer is underbilled or if no bill is sent for developed land, the county may back bill for a period of up to four years but shall not assess penalties for any delinquency due to the failure to send a bill or an under billing.

(d) Payments. Any partial monthly payments made to the county water system shall be applied to stormwater fees before being applied to water and sewer fees. Customer shall be required to make payments

necessary to keep the water and/or sewer fees current.

(e) Delinquent accounts. Amounts due not paid within 30 days from the due date are delinquent.

(f) Adjustments. The stormwater manager shall administer the procedures and standards for the adjustment of the stormwater service fee.

(1) If a customer believes their stormwater service fee is incorrect, the customer may seek an adjustment of the stormwater service fee allocated to a property at any time by submitting the request in writing to the stormwater manager and setting forth in detail the grounds

upon which relief is sought.

(2) If necessary, customers requesting the adjustment shall be required, at their own expense, to provide supplemental information to the

stormwater manager, including, but not limited to, a survey certified by a registered land surveyor or a professional engineer of the impervious surfaces on the subject property.

Submittal of this information shall be required if stormwater manger cannot make a determination based on county water system staff inspection and/or review of existing county aerial photography.

(3) Once a completed adjustment request and all required information are received by the stormwater manager, the stormwater manager shall have 30 calendar days within which to render

a written decision. Concurrent payment of any charges allocated to the property is not required as a condition precedent to this request for review.

(4) In considering an adjustment request, the stormwater manager shall consider whether the calculation of the stormwater service fee for the property is correct.

(5) The stormwater manager's decision shall be in writing and will be mailed or emailed to the address provided on the adjustment request, and service shall be complete upon mailing or emailing.

(6) If the result of an adjustment is that a refund is due the applicant, the refund will be applied as a credit on the applicant's next stormwater bill.

History

The history line the source prints at the end of the section.

(Amd. of 11-20-25)

Meetings that refer to this section

Found 1: meetings of this government whose minutes or machine transcripts name this section, or an ordinance in its history line, newest first. Found by rule from those records' own words. A reference is a pointer to another record, not a statement that the section applies or was changed.

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:cobb-county/code/122-314@2025-11-20-e4cf40ad8c

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.