(a) The director has the discretion to require monitoring of intensity levels at alternate locations not under the ownership or control of the developer, user, or blaster if such is warranted based upon complaints received by the county after the blasting activity begins. These alternate locations may be inside or outside the overall development project boundary. (b) Blast intensity may not exceed any of the following limits: (1) Blasting vibration-frequency limits: The velocity/shock wave of any blast shall not exceed 2" PPV at 40 Hz or greater. At lower frequencies, the county shall use the established limits in the vibration criteria as presented in the U.S. Bureau of Mines RI 8507, as may be amended from time to time. (2) Air blast limits: 140db or as defined by the U.S. Bureau of Mines RI 8485, as may be amended from time to time.