Sec. 26-74. Local development permits.

About this text

  • As published by Municode, current through 2025-02-04
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Local development permit requirements. No regulated activity will be allowed within the wetland protection district without written permission from the county administrator or his designee in the form of a local development permit. Issuance of a local development permit is contingent on full compliance with the terms of

this article and other applicable regulations. All activities that are not exempted in subsection (b) below or by other local development ordinances, shall be prohibited without prior issuance of a local development permit. If the area proposed for development is located within 50 feet of the wetland protection district boundary, as determined from the generalized wetland map, a U.S. Army Corps of Engineers determination shall be required. If the Corps determines that wetlands are present and that a section 404 permit or letter of permission is required, a local development permit will be issued only following issuance of the section

404 permit or letter of permission.

(b) Permissible uses (use as a right). The following uses shall be allowed as a right within the wetland protection district to the extent that they

are not prohibited by any other ordinance or law and provided they do not require structures, grading, fill, drainage, or dredging except as provided herein.

(1) Operations conducted during normal silvicultural activities, including minor dredge and fill associated with road construction, harvesting, and reforestation practices provided they meet the performance standards and road construction best management practices required under section 404 of the Clean Water Act.

(2) Conservation or preservation of soil, water, vegetation, fish, and other wildlife, provided they do not affect waters of Georgia or of the United States in such a way that would require an individual 404 permit.

(3) Outdoor passive recreational activities, including fishing, bird watching, hiking, boating, horseback riding, and canoeing.

(4) Forestry practices applied in accordance with best management practices approved by the Georgia Forestry Commission.

(5) The cultivation of agricultural crops. Agricultural activities shall be subject to best management practices approved by

the Georgia Department of Agriculture.

(6) The pasturing of livestock provided that riparian wetlands are protected, that soil profiles are not disturbed and that approved best management practices are followed.

(7) Education, scientific research, and nature trails.

(8) Temporary emergency permit. A temporary emergency permit can be issued by the county administrator or his designee

for the following reasons:

a. Maintenance or repair of lawfully located roads or structures and of facilities used in the service of the public to provide transportation, electric, gas, water, telephone, telegraph, telecommunication or other services,

provided that such roads, structures, or facilities are not materially changed or enlarged and that, prior

to the commencement of work, written notice has been given to the county and provided that the work is conducted using best management practices to ensure that flow and circulation patterns, and chemical and biological characteristics of the wetland, are not impaired and that any adverse effect on the aquatic environment will be minimized.

b. Temporary water level stabilization measure with silvicultural operations, provided that they are necessary to alleviate abnormally wet or dry conditions that would have an

adverse impact on the conduct of silvicultural activities if not corrected.

c. Limited ditching, tilling, dredging, excavating, or filling done solely for the purpose of maintaining or repairing existing drainage systems necessary for the cultivation of agricultural crops, provided that the maintenance or repair activity does

not result in the impairment, alteration, or loss of wetlands not previously subject to agricultural and silvicultural use under the terms and

provisions of this subsection (b).

d. Limited excavating and filling necessary for the repair and maintenance of piers, walkways, nature trails, observation decks, wildlife

management shelters, boathouses, or other similar water-related structures, provided that they are built on pilings to allow unobstructed flow of

water and preserve the natural contour of the wetland.

(c) Site plans. Applications for a development permit within the generalized wetland protection district shall include a site plan, drawn at a scale of 1" = 50', (the county may approve a different scale where necessary to clearly provide the required information) with the following information:

(1) A map of all planned excavation and fill, including calculations of the volume of cut and fill involved, cross-sectional drawings showing existing and proposed grades.

Elevations, horizontal scale, vertical scale must be shown on the cross-sectional drawings.

(2) Location, dimensions and area of all impervious surfaces, both existing and proposed, on the site and adjacent to the site for a distance of ±200 feet.

(3) The orientation and distance from the boundaries of the proposed site to the nearest bank of an affected perennial stream of water body.

(4) Elevations of the site and adjacent lands within 200 feet of the site at contour intervals of no greater than two feet.

(5) Location and detailed design of any spill and leak collection systems designed for the purpose of containing accidentally released hazardous or toxic materials.

(6) All proposed temporary disruptions or diversions of local hydrology.

(d) Activities to comply with site plan. All development activities or site work conducted after approval of the site plan shall conform with the

specifications of said site plan. The site plan may be amended only with the approval of the county.

The county may require a bond up to the larger of $5,000.00 or $1,000.00 per acre of project area and with surety and conditions sufficient to secure compliance with the conditions and limitations set forth in the permit. The particular amount and conditions of the bond shall be consistent with the purposes of this article. In the event of a breach of condition of any such bond,

the county may collect such bond or institute an action in a court of competent jurisdiction upon such bond and prosecute the same to judgement and execution.

(e) Filing fee. At the time of the application, the applicant shall pay a filing fee specified by the county. Filing fees up to the larger of $500.00 or $100.00 per acre may be required to evaluate the application. This fee may be used to retain expert consultants who will provide services pertaining to functional assessment and mitigation measures as deemed necessary by the county. In any case, the filing fees shall not be less than the

amount necessary for evaluation of the application in a manner consistent with the intent of this article.

(f) Enforcement authority. The county administrator or his designee is hereby established as the administrator of this article.

(g) Review procedure. The application shall be made to the administrator with a copy to such parties which may be designated by the county and will be reviewed within 60 days or in accordance with established review procedures for the type of development being considered, whichever

is greater. The review period shall include the preparation of findings (approval or disapproval) by the county administrator's office. The applicant will receive written notification of the findings thereof. If the review process is not completed within the time period specified herein, the application is considered to be approved for the

purpose of this article.

(h) Appeals. Decisions on permit applications made by the administrator or his designee may be appealed to the county administrator. The appeal must be made within ten days of the decision rendered by the county administrator. A public hearing notice shall be printed in local newspapers at least 15 but not more than 45 days prior to the hearing. Any person may offer testimony at

the hearing. The decision of the county commission may be appealed to a court of competent jurisdiction, as discussed in section 26-76.

(i) Duration of permit validity.

(1) If construction described in the development permit has not commenced within 12 months from the date of issuance, the

permit shall expire.

(2) If construction described in the development permit is suspended or abandoned after work has commenced, the permit

shall expire 12 months after the date that work ceased.

(3) Written notice of the pending expiration of the development permit may be issued by the county administrator.

History

The history line the source prints at the end of the section.

(Ord. No. 99-3, § 4, 6-22-99)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:colquitt-county/code/26-74@2025-02-04-86787fd58c