Columbia County · Code of Ordinances
Part II - CODE OF ORDINANCES / Chapter 34 - ENVIRONMENT / Article III - SOIL EROSION, SEDIMENTATION AND POLLUTION CONTROL
Sec. 34-70. Land disturbance application/ permit process.
About this text
- As published by Municode, current through 2026-02-17
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) General. The property owner, operator, developer and designated planners and engineers shall design and review the general development plans and detailed plans and requirements of the county that affect the tract to be developed and the area surrounding it. They shall review the zoning ordinance, stormwater management ordinance, subdivision ordinance, flood damage prevention ordinance, this article, and other ordinances which regulate the development of land within the jurisdictional boundaries of the county. However, the owner and/or operator are the only parties who may apply for and obtain a permit.
(b) Application requirements.
(1) Except as otherwise specifically provided by this article, no person shall conduct any land-disturbing activity within the jurisdictional boundaries of Columbia County, Georgia without first submitting to the county those documents specified for the activity in the then-current LDP table.
(2) The documentation package shall be submitted to the development services division and must include three copies of the applicant's plan with supporting data as specified in the LDP table, as necessary to demonstrate that the proposed land-disturbing activity will comply with
this ordinance or qualifies for an appropriate exemption. Where the LDP table specifies an ESPC plan, the documentation submitted shall contain a signed certification stating that the plan preparer or the designee thereof visited the project site prior to creation of the plan
in accordance with EPD rule 391-3-7-.10.
(3) For major land disturbance permits as defined in the LDP table, an administrative fee, in the amount of $5.00 per disturbed acre (or portion thereof) shall
be charged and collected by the county for each project under this article. The administrative fee shall be paid at the time the ESPC plan is submitted to the county. In addition to such county administrative fee, permit fees will also be assessed pursuant to paragraph (5) subsection (a) of O.C.G.A. § 12-5-23, provided that such fees shall not exceed $80.00 per acre of land-disturbing activity, and these fees shall be calculated and paid by the primary permittee as defined
in the applicable state general permit for each acre of land-disturbing activity included in the project, the planned development or each phase of development. All applicable fees shall be paid prior to issuance of the land disturbance
permit. Half of such fees shall be submitted to the county, and the other half to EPD in accordance with the applicable
state general permit; except that any and all fees due from an entity which is required to give notice pursuant to O.C.G.A. § 12-7-17(9) or (10) shall be submitted in full to the EPD.
(4) Immediately upon receipt of an application and plan for a permit, the county shall review the plan and shall approve
or disapprove the plan within 35 days of receipt. Failure of the county to act within 35 days shall be considered an approval of the pending plan. No permit will be issued unless the plan has been approved by the county, and any variances required by section 34-69, all fees have been paid, and bonding, if required as per section 34-70, have been obtained.
(5) Denial of permit. If a permit applicant has had two or more violations of previous permits, this article, or the Georgia Erosion and Sedimentation Act, as
amended, within three years prior to the date of filing of the application under consideration, the county may deny the permit application pursuant to O.C.G.A.
§ 12-7-7(f)(1).
(6) Bond requirement. The county may require the permit applicant to post a bond in the form of government security, cash, irrevocable letter of credit, or any combination thereof up to, but not exceeding, $3,000.00 per acre or fraction thereof of the proposed land-disturbing activity,
prior to issuing the permit. If the applicant does not comply with this article or with the conditions of the permit after issuance, or the bond, the county may call the bond or any part thereof to be forfeited
and may use the proceeds to hire a contractor to stabilize the site of the land-disturbing activity and bring it into compliance. This bond shall not be required in the event a performance and maintenance bond, as set forth in Sec 74-45, has been provided to the county for the same improvements and for conditions of the Land Disturbance Permit and the Notice of Termination.
(c) Plan requirements.
(1) Plans must be prepared to meet the minimum requirements as contained in section 34-69 and the required documents section of the LDP table. The plan for the land-disturbing activity shall
consider the interrelationship of the soil types, geological and hydrological characteristics, topography, watershed, vegetation, proposed permanent structures including roadways, constructed waterways, sediment control and storm water management facilities, local ordinances and state laws.
(2) Maps, drawings, and supportive computations shall bear the signature/seal of a certified design professional. Persons
involved in land development design, review, permitting, construction, monitoring, or inspections or any land-disturbENVIRONMENT § 34-70 ing activity shall meet the education and
training certification requirements, dependent on his or her level of involvement with the process, as developed by the commission and in consultation with
the division and the stakeholder advisory board created pursuant to O.C.G.A. § 12- 7-20. Data required for ESPC plan shall include, at minimum, all the information required from the appropriate erosion, sedimentation and pollution control plan review checklist established by the commission as of January 1 of the then current year.
(3) Plan phasing.
a. Initial phase plan must include provision for sediment storage of 67 cubic yards per drained acre, which shall sediment storage, shall remain in place until permanent stabilization is established. Initial phase plan must also include, at minimum,
construction entry/exit, tree-save fence (if applicable) and any other BMPs necessary to prevent sediment from leaving the site such as perimeter silt fence, inlet protection
on existing storm drain structures, diversions, check dams, temporary ground cover. Limits of disturbance for the initial phase shall be the areas needed to install initial BMPs.
b. The intermediate phase shall show at minimum rough grading, utility construction, and sediment storage.
BMPs should include at minimum and as and where appropriate, initial inlet protection, additional silt fence as needed, any revised sediment storage needed as drainage basins and surface gradients are altered, outlet protection, retrofit if applicable, matting with temporary or permanent vegetation as needed, temporary down drains, filter rings.
c. If necessary, a platting phase may be utilized to demonstrate all BMP's to be in place prior to building construction, including areas to be temporarily stabilized that will be disturbed during building construction, permanent ground cover such as pavement, vegetation, matting,
revised sediment storage, and any other BMPs needed before property ownership changes as part of a common development.
d. Final phase shall show at minimum finished grade, curbing and paving if applicable, and building construction, if applicable. BMPs should include, at minimum, permanent
vegetation, appropriate inlet protection, and sediment storage to remain until final stabilization.
e. Post construction phase shall include at minimum water quality controls depicting stormwater management systems designed to remove 80 percent of the post construction suspended solids and any other watershed or site specific water quality requirements. The plan shall include specific information regarding maintenance, operation, and delegation of responsibility for the
system.
(d) Minor and major land disturbance permits.
(1) Permits shall be issued or denied as soon as practicable but in any event not later than 45 days after receipt or by the county of a completed application, providing variances and bonding are obtained, where required and all applicable fees as
specified in the county fee schedule have been paid prior to permit issuance. The permit may include conditions under which the activity may be undertaken.
(2) No permit shall be issued by the county unless the ESPC plan has been approved and the county has affirmatively determined that the plan is in compliance with this article, any variances required by section 34-69 are obtained,
bonding requirements, if necessary, as per section 34-70 are met and all ordinances and rules and regulations in effect within the jurisdictional boundaries of the county are met. If the permit is denied, the reason for denial shall be
furnished to the applicant.
(3) If the tract is to be developed in phases, then a separate permit may be required for each phase.
(4) The permit may be suspended, revoked, or modified by the county, as to all or any portion of the land affected by the plan, upon finding that the land-disturbing activity is not in compliance with the approved ESPC plan or the permit or that the holder or his successor is in violation of this article. A holder of a permit shall notify any successor as to all or any portion of the land affected by the approved plan of the conditions contained in the permit.
(5) Any land-disturbing activities by the county shall be subject to the requirements of this article, and any other ordinances relating to land development,
as are applied to private persons.
(6) A preconstruction conference as required by the LDP table for minor and major land disturbance permits shall be held and must be attended by the design professional, owner, and contractor along with appropriate county staff. A land disturbance permit placard and three sets of stamped approved plans will be distributed at this conference. The placard must be posted at the construction entrance prior to the initiation of any land-disturbing activity.
(7) Once approved, the permit is effective until completion of the approved land disturbing activity, or suspended or revoked in accordance with this article;
however, if the land disturbing activity does not commence within 12 months from the date issued, or construction ceases for a period of 90 days, this permit will become null and void.
(Ord. No. 16-16, § 1(Exh. A), 6-7-2016; Ord. No.
18-02, § 1(Exh. A), 2-6-2018; Ord. No. 18-13, § 1(Exh. A), 12-4-2018; Ord. No. 19-05, § 1(Exh.
A), 4-16-2019)