Sec. 74-45. Performance and maintenance bond.
About this text
- As published by Municode, current through 2026-02-17
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) A performance and maintenance bond, letter of credit, cash bond, or other equivalent form of security as approved by the county attorney, running in favor of the county, in a minimum amount of $5,000.00 or any amount equal to at least ten percent of the actual construction cost of all improvements to be dedicated to the county, whichever is greater, shall be posted with the county by all subdivid-ers or persons where street or other improvements are made and offered to the county for acceptance and maintenance except as noted in this section. The performance and maintenance bond, cash bond, letter of credit or other equivalent form of security shall guarantee all improvements against defects in design, material and workmanship and further guarantee that all such improvements shall be installed and maintained in first class condition for the required period and faithful performance by the subdivider or other person of all provisions of this chapter.
(1) Any bond, except cash bond, or letter of credit or other equivalent form of approved security shall be on forms supplied by
the county and shall not be terminated or otherwise allowed to expire prior to the satisfactory completion of the maintenance period under section 74-46, or until
released by the board of commissioners.
Such bond, cash bond, letter of credit or other equivalent form of approved security along with evidence of payment of the
required premiums shall be filed with the county.
(2) Such bond, cash bond, letter of credit or other equivalent form of security shall be posted prior to commencement of construction. No preliminary plat shall be approved or recorded by the county and
no construction shall commence until and unless a satisfactory bond is posted.
(3) Separate bonds required by this section shall be required for each subdivision
unit, phase or like entity approved by the county pursuant to this chapter.