(a) The following conditions shall apply to the compliance schedule required in section 86- 153(7): (1) The schedule shall contain progress increments in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment required for the user to meet the applicable pretreatment standards. Such events include, but are not limited to, hiring an engineer, completing preliminary and final plans, executing contracts for major components, commencing and completing construction and beginning and conducting routine operation. No increment set forth in this subsection shall exceed nine months. (2) The user shall submit a progress report to the director no later than 14 days following each date in the schedule and the final date of compliance including, as a minimum, whether or not the user complied with the increment of progress, the reason for any delay and, if appropriate, the steps being taken by the user to return to the established schedule. No more than nine months shall elapse between such progress reports to the director. (3) Compliance with categorical pretreatment standards by existing users shall be no later than three years from the date the standard becomes effective, unless a shorter compliance time is specified. Within the shortest feasible time, not to exceed 90 days, new sources must meet all applicable pretreatment standards. (b) An industrial user who fails or refuses to comply with an interim or final date of compliance may be deemed by the director to be in violation of the wastewater discharge permit.