Sec. 12-219. General requirements for all ground mounted solar energy systems and/or battery storage facilities.

About this text

  • As published by Municode, current through 2025-12-15
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The following requirements apply to all systems or facilities, in addition to the specific requirements in this article that apply to intermediate and large scale SESs respectively.

(a) Solar access. Consistent with O.C.G.A. § 44-9-20 et seq., a property owner may obtain a solar easement from another property owner for the purpose of ensuring a ground mounted SES adequate exposure to sunlight.

(b) Impervious surface. Ground mounted structures and components of a system or facility, including transformers and foundations, shall be considered impervious. How- ever, the panels of a ground mounted SES shall be considered pervious if they maintain sheet flow and allow for water to infiltrate under and around them through a pervious surface and into the subsoil.

(c) Lighting. To reduce light pollution, lighting of a system or facility shall:

(1) Be limited to the minimum reasonably necessary for its safe operation;

(2) Be directed downward where reasonably feasible;

(3) Incorporate full cut-off fixtures; and

(4) Reasonably utilize motion sensors.

(d) Decommissioning. Unless otherwise approved by the board of commissioners, decommissioning shall begin no later than 12 months after a system or facility has ceased to generate or store electricity and/or thermal energy:

(1) For a system or facility allowed without a permit (prior to April 1, 2023), within six months of the beginning of decommissioning, the SES and all structures associated with it shall be removed, all materials shall be recycled or otherwise reused to the extent reasonably practicable, and the property shall be returned to its condition prior to the installation of the SES or to some other condition reasonably appropriate for the designated land use; and

(2) For a system or facility (after April 1, 2023) allowed with a permit, the system or facility shall be decommissioned in accordance with the most recent decommissioning plan included in the application and approved by the county manager or his designee.

(e) Airports. Any system proposed within a three mile radius of an airport or helipad shall present evidence that they have consulted with the appropriate authority regarding the energy system before construction and completed a review process with the Federal Aviation Administration (FAA). This review from the FAA shall indicate that the proposed facility shall not interfere with the normal operation of aircraft in the area.

Systems shall not be placed in the vicinity in a manner that would interfere with the airport flight patterns.

(f) Noise. Systems and facilities must adhere to the noise standards to avoid contribution to excessive noise pollution. The following noise limits shall apply:

(1) The continuous sound level generated by the system shall not exceed 35 decibels, measured at a distance of 25 feet from the property line of the operation.

(g) Signage.

(1) Shall display signs (a) stating the risks that may result from contact with a system or facility, (b) identifying the owner or operator of the system or facility, and (c) providing a 24-hour emergency contact phone number;

(2) Shall have signs that contain educational information about the system or facility.

(h) Visual buffers.

(1) Systems and facilities shall have and maintain, to the extent reasonably practicable, a visual buffer from the ground up to six feet high of natural vegetation, plantings, earth berms, and minimum fencing six feet high that provides a reasonable visual and lighting screen to reduce the view of and potential reflection from the system or facility to structures on adjacent lots (including those lots located

across a public right-of-way). The existing natural tree growth and natural land forms along the system or facility perimeter may create a sufficient buffer and shall be preserved when reasonably practicable. Any visual buffer must be established and maintained in accordance with the most recent visual buffer plan submitted by the applicant and approved by the county manager or his designee.

History

The history line the source prints at the end of the section.

(Ord. of 11-18-2024(1); Ord. of 11-3-2025, § 4)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:dodge-county/code/12-219@2025-12-15-89427b921c