(a) Generally. Plans must be prepared to meet the minimum requirements contained in this section and section 18-207. Conformance with the minimum requirements may be attained through the use of design criteria in the current issue of the Manual for Erosion and Sediment Control in Georgia, published by the state soil and water conservation commission as a guide;
or through the use of alternate design criteria which conform to sound conservation and engineering practices. The Manual for Erosion and Sediment Control in Georgia is hereby incorporated by reference into this article. The plan for the land disturbing activity shall consider the interrelationship of the soil types, geological and hydrological characteristics, topography, watershed, vegetation, proposed permanent structures including roadways, constructed waterways, sediment control and stormwater management facilities, local ordinances and state laws.
(b) Data required. Data required for the site plan are as follows:
(1) Notes or narrative to be located on the site plan in general notes or in erosion and sediment control notes.
(2) Description of existing land uses at the project site and description of the proposed project.
(3) Name, address and phone number of the property owner.
(4) Name and phone number of a 24-hour local contact who is responsible for erosion and sedimentation control.
(5) Size of project, or phase under construction, in acres.
(6) Activity schedule showing anticipated starting and completion dates for the project, including the statement in bold letters that the installation of erosion and sedimentation control measures and practices shall occur prior to or concurrent with land disturbing activities.
(7) Stormwater and sedimentation management systems-storage capacity, hydrologic study and calculations, including off-site drainage areas.
(8) Vegetative plan for all temporary and permanent vegetative practices, including species, planting dates and seeding, fertilizer, lime and mulching rates. The vegetative plan should show options for yearround seeding.
(9) Detailed drawings for all structural practices. Specifications may follow guidelines set forth in the Manual for Erosion and Sediment Control in Georgia.
(10) Maintenance statement: "Erosion and sedimentation control measures will be maintained at all times. Additional erosion and sedimentation control measures and practices will be installed if deemed necessary by on-site inspection."
(c) Certification of plans; contents. Maps, drawings and supportive computations shall bear the signature/seal of a registered or certified professional in engineering, architecture, landscape architecture, land surveying, or erosion and sedimentation control. The certified plans shall contain:
(1) Graphic scale and north point or arrow indicating magnetic north.
(2) Vicinity maps showing location of project and existing streets.
(3) Boundary line survey.
(4) Delineation of disturbed areas within project boundary.
(5) Existing and planned contours, with contour lines drawn with an interval in accordance with the following:
Map Scale Ground Slope Contour Interval, feet 1 inch = 100 feet or larger scale Flat 0—2% Rolling 2—8% Steep 8% +
0.5 or 1 1 or 2
2.5 or 10
(6) Adjacent areas and features areas such as streams, lakes, residential areas, etc., that might be affected should be indicated on the plan.
(7) Proposed structures or additions to existing structures and paved areas.
(8) Delineate the 25-foot horizontal buffer adjacent to state waters and the specified width in MRPA areas.
(9) Delineate the 100-foot horizontal buffer along designated trout streams, where applicable.
(10) Location of erosion and sedimentation control measures and practices using coding symbols from the Manual for Erosion and Sediment Control in Georgia, chapter 6.
(d) Maintenance of control practices. Maintenance of all soil erosion and sedimentation control practices, whether temporary or permanent, shall be at all times the responsibility of the property owner.