If, on or before the 11th day as described in section 64-62(b), an application is deemed complete, the Emanuel County Board of Commissioners shall approve or deny an application within ten calendar days unless a joint meeting between the applicant and the Emanuel County Board of Commissioners is deemed necessary. (a) If a joint meeting is deemed necessary, the joint meeting must occur within 15 calendar days of notification of completion and the joint meeting shall include: (1) Where the applicant is going to conduct work; (2) When the work will be conducted; (3) What type of work will be done; (4) Who the Emanuel County Board of Commissioners can contact for specific details or related questions; and (5) Any permit seeking approval under application. (6) Following a joint meeting between the applicant and the Emanuel County Board of Commissioners shall deny or approve the application within ten calendar days. (b) Upon final approval, any required permit permitted shall be deemed issued.