(a) Gilmer County shall determine whether an application is incomplete and notify the applicant, by email, of the determination by Gilmer County within ten calendar days of receiving an application.
(b) If Gilmer County does not respond to the applicant on whether the application is incomplete, within ten calendar days, the application shall be assumed to be complete on the 11th day.
History
(Res. No. 19-174, 11-14-2019)