Lots on which a Solar Farm is located shall be subject to the following regulations: A. Removal Requirement/Decommissioning. Any large-scale ground-mounted solar energy system which has reached the end of its useful life or has been abandoned as defined by these regulations shall be removed. The owner or operator shall physically remove the installation no more than 150 days after the date of discontinued operations. The owner or operator shall notify the Building Official by certified mail of the proposed date of discontinued operations and plans for removal. Decommissioning shall consist of: 1. Physical removal of all solar energy systems, structures, equipment, security barriers and transmission lines from the site. 2. Disposal of all solids and hazardous waste in accordance with local, state, and federal waste disposal regulations. 3. Stabilization or re-vegetation of the site as necessary to minimize erosion. B. Abandonment. Absent notice of a proposed date of decommissioning or a variance issued by the Grady County Board of Commissioners, a Solar Farm shall be considered abandoned when it fails to operate for more than one year. If the owner or operator of the Solar Farm fails to remove the installation in accordance with the requirements of this section within 150 days of abandonment or the proposed date of decommissioning, Grady County shall have the right to enter and remove any abandoned, hazardous, or decommissioned Solar Farm equipment or ground-mounted solar energy system. As a condition of a Site Plan approval for the installation of a new Solar Farm, the applicant and landowner shall agree to allow entry to remove an abandoned or decommissioned Solar Farm, in whole or in part, and further agree to be jointly and severally liable with the landowner for any cost incurred by Grady County in decommissioning the site. C. Surety Bond. Prior to commencement of construction of a Solar Farm, the permit holder shall provide a surety bond, in the form directed by the Building Official insuring the permit holder's compliance with decommissioning, which shall remain in full force and effect throughout the life of the Solar Farm and continuing until the completion of its proper decommissioning, in an amount equal to at least 10 [percent] of the total construction costs of the Solar Farm. This surety bond shall be in the form of a new or modified guaranty to ensure the availability of funds for such decommissioning costs. The guaranty shall be from an entity having at the time of delivery of such guaranty, a senior unsecured long term debt rating of A or better from Standard and Poor's and A2 or better from Moody's Rating Agencies. D. Height Limit. Solar Collector height, which shall be measured from the highest finished grade below each solar panel to the top of that panel, shall not exceed 15 feet.