Unless a special agreement as provided for in this article exists, pretreatment as mentioned in section 13.10.1220 shall mean the following:

A. Removal of all prohibited materials and correction of all unacceptable conditions mentioned in Section 13.10.1220 of this chapter. Pretreatment systems or units shall be designed such that the following pollutants are not exceeded based upon representative samples of the discharge to the control authority's sewers, taken on days of normal plant operation, with tests being performed as detailed in 40 CFR 136, including, but not limited to, "Standard Methods for the Examination of Water and Wastewater", latest approved edition, published by the American Public Health Association and others:

Pollutant Maximum Level BOD 300 mg/L Total suspended solids 300 mg/L Fat, oil, grease 100 mg/L Phosphorus 7 mg/L TKN 40 mg/L

B. The user discharge concentration limits listed in section 13.10.1220B.(2) shall be the limits required on wastewater discharge permits. Such limits may therefore be used as a guide in pretreatment facility design and operation. If the user

exceeds these limits or is found in violation of this article, the user is in a state of violation. In the event that the POTW

influent level is exceeded or a disruption of the sewage treatment plant process occurs due to an excessive level of one or more of these user discharge concentration limits, the board of commissioners may alter the user discharge concentration limits sufficiently to protect the plant and its receiving stream. Such modifications shall apply to all users. In the event of toxicity being found in a POTW, the

director may at his discretion require industrial users to participate in a toxicity reduction evaluation in accordance with

the provisions of the control authority POTW's NPDES permits.

C. Control over quantities and rates of discharge referred to in section 13.10.1220B.(2) as applied to major contributors means that the daily plant discharges shall be spread as uniformly as possible over the entire 24-hour period. In

no case shall the discharge in one continuous eight-hour period exceed 50 percent of the total 24-hour discharge.

D. The pretreatment or equalization of waste flows, and the design for installation of plants and equipment for the pretreatment or equalization of waste flows, shall be subject to the review and approval of

the director and the building official and shall be subject to the requirements of all applicable codes, ordinances and laws.

Any subsequent alterations or additions to such pretreatment or flow control facilities shall not be made without due notice to, and prior approval of, the director.

E. All users shall comply with the pretreatment standards as set forth in 40 CFR, Part 403.

History

The history line the source prints at the end of the section.

(Res. of 1-8-09(1), §§ 1, 2(Exh. A))

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hall-county/code/13.10.1340@2026-05-28-337463028a

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Hall County Code of Ordinances, 13.10.1340. Pretreatment design parameters | Georgia Commons