Sec. 10-182. State and health department permits required.

About this text

  • As published by Municode, current through 2023-06-06
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) State issued land disturbance permit. All applications for commercial construction must be accompanied by a land disturbance (grading) permit issued by the state environmental protection division if disturbing over one acre. The site and building plans will be inspected by the building department and, if over one acre of land is to be disturbed, the soil and erosion plans will be inspected by the state environmental protection division.

(b) Septic permit or sewer tap-on approval. If the building is to be served by septic system a copy of the septic permit from the county health department must be furnished. If the building is to be served by sewer a letter from the provider, indicating tap-on is permitted.

When the building plans are approved and information is furnished that the sewer or septic system is adequate for the proposed use the building permit may be issued.

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:haralson-county/code/10-182@2023-06-06-7e28e927c3

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Haralson County Code of Ordinances, Sec. 10-182. State and health department permits required | Georgia Commons