Duties of the public works director shall include, but shall not be limited to:
(1) Review all development permits to assure that the permit requirements of this
article have been satisfied.
(2) Review proposed development to assure that all necessary permits have been
received from governmental agencies from which approval is required by federal or state law, including section 404 of the
Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. 1334.
Require that copies of such permits be provided and maintained on file.
(3) When base flood elevation data or floodway data have not been provided in accordance with section 38-37, then the
public works director shall obtain, review and reasonably utilize any base flood
elevation and floodway data available from a federal, state or other sources in order to administer the provisions of
division 2 of this article.
(4) Verify and record the actual elevation in relation to mean sea level (or highest
adjacent grade) of the lowest floor, including basement, of all new or substantially improved structures in accordance with
section 38-46(2).
(5) Verify and record the actual elevation, in relation to mean sea level to which any
new or substantially improved nonresidential structures have been floodproofed, in accordance with section 38-46(2).
(6) When floodproofing is utilized for a structure, the public works director shall obtain certification of design criteria from a registered professional engineer or
architect in accordance with section 38-46(1)c. and section 38-82(2) or 38-84(2).
(7) Notify adjacent communities and the state department of natural resources prior to any alteration or relocation of a
watercourse and submit evidence of such notification to the Federal Emergency Management Agency (FEMA).
(8) For any altered or relocated watercourse, submit engineering data/analysis within
six months to the FEMA to ensure accuracy of community flood maps through the letter of map revision process. Assure flood-carrying capacity of any altered or relocated watercourse is maintained.
(9) Where interpretation is needed as to the exact location of boundaries of the areas of special flood hazard (for example, where there appears to be a conflict between a mapped boundary and actual field conditions) the public works director shall make the necessary interpretation. Any
person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation as provided in this article.
(10) All records pertaining to the provisions of this article shall be maintained in the office of the public works director and
shall be open for public inspection.
(11) Review all permit applications to determine whether proposed building sites will be reasonably safe from flooding.
(12) Make substantial damage determinations following a flood event or any other event that causes damage to structures
in flood hazard areas.
History
(Ord. of 10-22-2019(2))