Sec. 28-84. Construction standards and specifications.

About this text

  • As published by Municode, current through 2019-01-10
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Each non-public roadway, drive and ramp in this county must be constructed in a workmanship-like manner, taking into consideration the terrain, soil type and anticipated usage. In addition, each non-public roadway, drive and ramp must meet as a minimum the following specifications and requirements:

(1) All road and street rights-of-way conveyed to the county must have an overall minimum width of 80 feet, with a graded roadbed of not less than 30 feet in the center.

In addition, the outside edges of the graded road must be graded, ditched and sloped appropriately to accommodate all normal water runoff from the graded roadbed.

(2) All ramps constructed to join or connect a non-public driveway with a public or non-public roadway must be at least 20 feet wide if the non-public roadway or drive is a private driveway for a private single-family residence, and 30 feet wide if the non-public roadway is for any other purpose other than a driveway for a private single-family residence.

(3) The roadway, drive or ramp must be constructed of materials normally suitable for the type of roadway, driveway or ramp being constructed and must comply or meet with the standards of the current edition of the current edition of the state department of transportation standard specifications or such other standards which this board may adopt from time to time without the necessity of amending this article.

(4) Ditches, pipe and other water drainage and run-off measures will be provided and installed by applicant for each such roadway, ramp and drive as required to adequately drain and protect such roadway, ramp, or drive as well as the adjoining public and private roadways which will be affected by the water runoff from such non-public roadway, ramp, or drive. The final resolution of such drainage measures must also provide for the protection from any potential runoff damage to any then proposed streets or roadways that may be subsequently affected by the water runoff from such non-public roadway, ramp or drive.

(5) Construction of the roadway, driveway or ramp shall not interfere with, impede, or create a hazard to existing drainage or traffic.

(6) All work will be required to be performed in such a manner as not to present the county with an inferior or substandard roadway which would result in additional expenditures or undue future maintenance by the county.

(7) Paving is not mandatory. However if a paving is to be done, the roadway, drive or ramp must comply with all requirements of the state department of transportation standard specifications relating to paved county roads.

(8) Upon request of an applicant and if the board of commissioners determines it to be in the best interests of the public, the county may construct a ramp from a public right-of-way to the edge of applicant's private property, providing applicant pays in advance the cost of the pipe to be used. The county will not construct ramps from on or across non-public property or from non-public roadways.

(9) All pipe and other materials used by a landowner or applicant in the construction of a ramp, drive or roadway which is on, or subsequently becomes a part of, a public right-of-way become the property of the county and may not be removed by the applicant or landowner, regardless of whether the pipe or other materials were furnished by the landowner or the county.

(10) The location of the point of connection or joining with a public road must be first approved by the board of commissioners of the county or its authorized representative.

History

The history line the source prints at the end of the section.

(Ord. of 6-12-1984, § 5; Ord. of 2001, § 1)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:jeff-davis-county/code/28-84@2019-01-10-cc646ee90a