(a) In the event the county commissioners should elect to widen or relocate any existing road or to make a new road in this county, the county commissioners reserve the right to require the utility owner to take up and relay such sections of the facility within the right-of-way as may be necessary from an engineering standpoint due to the making of any such new road, or the widening or relocating of such existing road; the taking up and relaying of all such lines, poles and facilities shall be at the sole expense of the utility owner. This work shall be completed within 15 working days after notification by the county commissioners, or within such other time as may be approved in writing by the county engineer or other designated official.
(b) In the event a utility owner should fail or refuse to take up and relay poles or other portions of its facilities as required above, the county commissioners shall have the right to take up or relay such poles or other facilities and bill the entire cost of same to the utility owner. Furthermore, no permits to install or relocate poles or other facilities shall be granted to any utility owner who is then currently refusing or failing to comply with this article.
History
(Ord. of 1-4-1983, §§ 8, 10)