Sec. 2-246. Purchase requisition.

About this text

  • As published by Municode, current through 2024-07-09
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) The purchase requisition initiates the procurement cycle. The receipt of a purchase requisition with the necessary information and required signature gives the authority for each specific purchase. A purchase order will not be issued unless authorized by a proper requisition. The purchase requisition makes the purchasing agent accountable for filling the needs as stated on the requisition. The signature of the department head is required on all purchase requisitions.

(b) The purchase requisition shall be used for the following:

(1) To request the purchase of supplies or services (except engineering and other professional services).

(2) To change or cancel an existing purchase requisition.

(3) To request price and delivery information on possible requirements.

(c) The purchase requisition will be a single part form available from central supplies.

The completed form is to be forwarded to the purchasing agent who will review the purchase requisition for the purpose of assuring that all required information is provided, that the price indicated is the "best price," that budget compliance/variance is known, and that contract compliance be discussed directly with the requisitioner.

(d) A purchase requisition shall include all of the following information:

(1) Date the purchase requisition is prepared.

(2) Complete ship-to address.

(3) Expenditure code number, line item of account.

(4) Indication whether the purchase is budgeted or unbudgeted.

(5) Proper numbers of fund, program, and expenditure chart of account.

(6) Project number (or name) if applicable.

(7) A definite date for completion should always be given. Terms such as "emergency" and "rush" may be used, but also include a firm date. The term "a.s.a.p."

should not be used.

(8) If known, one or more suppliers should be recommended. If the requisitioner feels a particular supplier should not be used, it should be so stated along with the purchase requisition with a brief explanation.

(9) The quantity requested should clearly identify measurable units such as pieces, sheets, pounds, gallons, feet, etc.

(10) Descriptions should be complete and detailed. Specifications should be written so that no guess work is required. If a specification such as color is not important, it should be so stated on the purchase requisition. If known, the manufacturer and part number should be shown.

(11) The unit price or an estimated unit price.

(12) The requisitioner should include on or attached to the purchase requisition any useful information whatsoever that will assist in making the best possible buy on the needed supplies or services

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:jefferson-county/code/2-246@2024-07-09-407748b28c

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.