(a) Electrical disconnect. The electrical disconnect switch shall be clearly identified and accessible at all times to emergency personnel. The owner must file a map with the Jefferson County Public Safety Department depicting where the disconnect switch is located.
The owner shall supply all emergency contact information to emergency personnel to have on file.
(b) Compliance. The developer/owner shall at all times construct and operate the facility in compliance with local, state and federal guidelines as to soil erosion and sedimentation, stormwater management, and all other environmental, cultural, and historical regulations. The owner shall operate the facility in compliance with any interconnection
requirements from appropriate public utilities or public utility regulatory agencies. The owner, operator, lessee, or any other third party who exercises control of the equipment shall provide notice to the building official of any changes in ownership or assignment of any obligations under any lease or operating agreement. Such notice shall include the identification of an individual representative of such part and contact information for the same, to include mailing address and telephone number. Any subsequent or successor lease or operating agreement affecting the solar farm shall be filed with the building official within 30 days of such agreement becoming effective.
(c) Failure to proceed and abandonment. The developer shall submit a decommission plan to the zoning board for approval. The decommissioning plan that contains the following:
(1) The name, address, telephone number, and e-mail address of the person(s) or entity(ies) responsible for implementing the decommissioning plan;
(2) A statement of conditions that require the decommissioning plan to be implemented;
(3) As part of decommissioning, a removal plan that identifies all structures, components, and non-utility-owned equipment that shall be removed;
(4) As part of decommissioning, a plan for recycling or otherwise reusing all materials to the extent reasonably practicable;
(5) as part of decommissioning, a restoration plan to return the property to its condition prior to the installation of the SES or to some other condition reasonably appropriate for the designated land use after the SES is removed; and
(6) A timeline to complete decommissioning.
Prior to the issuance of a certificate of occupancy, a bond or letter of credit will be required by the county in an amount to be determined by the planning commission or board of commissioners to cover the cost of removal and demolition of any facilities and structures and restoring the property to its natural state. In the event the developer/owner ceases operation of the solar collection facility, or begins but does not complete construction of the project, the developer/owner shall restore the site according to the decommission plan. Any solar collection device or combination of devices that is not operated for a continuous period of 12 months and for which there are no applications pending for permitted use of the structure at the end of such 12-month period, shall be considered abandoned, whether or not the owner or operator intends to make use of the device(s).
The owner of an abandoned solar collection device and the owner of the property where the abandoned solar collection device is located shall be under a duty to remove such device under the decommission plan. If such device(s) is not removed within a reasonable time, not to exceed three months after receipt of notice from the governing authority notifying the owner of such abandonment, the governing authority may remove the device(s) and place a lien upon the property for the costs of removal. The governing
authority may pursue all legal remedies available to it to ensure that abandoned device(s) is removed. Delay by the governing authority in taking action shall not in any way waive the governing authority's right to take action.
(d) Proof of insurance. The owner at the time of completion and all perpetual owners must provide the county building inspection department with a copy of the certificate of insurance providing proof of adequate coverage for property damage and commercial general liabilities.