All solar farms in the unincorporated areas of the county shall comply with the following standards:
(a) The following minimum setback distances shall be required for all system components for a solar farm project (exclusive of fencing and vegetative screening):
(1) Three hundred feet from all dwelling units, except where the owner of a dwelling unit agrees to lessen such distance by executing a signed written waiver of this requirement;
(2) One hundred feet from all public right-of-way frontages; and
(3) Fifty feet from all property boundaries, with the exception of property boundaries of adjoining parcels that are a part of a single solar farm project, as shown on the site plan. These property boundaries shall not be subject to this setback requirement. In such excepted case, a written waiver approved by the county and signed by the property owner(s) of all adjoining parcels included in the project shall be required.
(b) Power inverters and other sound-producing equipment shall be sited no less than 150 feet from any dwelling unit in place at the time of construction or installation.
(c) All solar farms shall be fenced in using a chain link fence with a height of at least six feet, as measured from the finished grade of the fencing perimeter, with anti-climb devices with three barbed wire line arms. Brightly colored signs no smaller than one foot by two feet shall be posted on the fence every 100 feet warning of danger and high voltage.
(d) Abutting residential properties shall be visually screened year round from any solar farms to the reasonable satisfaction of the county through any one of a combination of planting or existing evergreen vegetative screening or privacy fencing, all of which shall be at least six feet in height.
§ 53-13
(e) Clearing of natural vegetation shall be limited to that which is necessary for the construction, operation, and maintenance of the ground mounted solar photovoltaic installation and consistent with best practices for the preservation of natural areas or good husbandry of the land or forest.
(f) Any disturbed land shall be stabilized by a permanent seeding of perennial vegetation such as grass or other dense surface cover that will protect the soil surface from erosion, prevent sediment and runoff at the site from reaching downstream areas, and enhance the aesthetics of the site. It is recommended that a slow-growing, vegetative cover be utilized so that general maintenance of the growth can be kept to a minimum.
(g) The names of the manufacturers, installers, facility owners, and facility operators, and their addresses and phone numbers shall be posted on the required fencing at each entrance of a solar farm.
(h) All electrical interconnection and distribution lines within a solar farm's boundaries, except for power lines that leave the project or are within the substation, shall be underground. However, collector lines between sections within the farm may be overhead where economically advisable and consistent with common industry practice. The county may also grant written exceptions due to severe environmental or economic constraints and other considerations.
(i) Lighting of a solar farm and its accessory structures shall be limited to the minimum reasonably necessary for its safe operation and shall be reasonably shielded from abutting properties. Where feasible, lighting of a solar farm shall be directed downward and shall incorporate full cutoff fixtures to reduce light pollution.
(j) All solar farms shall comply with any other applicable requirements of the county code of ordinances.
(k) All solar farms shall have a lock box entry system at the primary entrance. The lock box entry system shall comply with the specifications of the International Fire Code.
(l) All solar farms shall have a written emergency response plan that shall be approved by the county's code enforcement department, sheriff's office, fire department, and emergency management agency. Each solar farm shall update its emergency response plan no later than January 1 of each year with a copy provided to all departments and agencies named in this subsection. The emergency response plan shall include the following:
(1) The phone number, email address, and street address for all manufacturers, installers, owners, and operators; and
(2) The phone number, email address, and mailing address for a representative of the solar farm responsible for responding to public inquiries; and
(3) The material safety data sheets that apply to any materials on the solar farm;
and
(4) The clearly marked means and instructions for shutting down the solar photovoltaic installation.
(m) Any solar farm that has not been in use for a period of 180 consecutive calendar days for its original purpose as approved by the county shall be deemed abandoned and shall not be authorized to recommence operations until a new application and inspection have been completed.
(n) The owners and operators of a solar farm and the owners of any real property on which it is located shall be jointly responsible for maintaining the solar farm.
(o) Permits for solar farms must include a contingent decommissioning plan, as specified in section 53-15.
(p) Solar panel placement should be prioritized to minimize or negate any solar glare onto nearby properties or roadways.
(q) A solar farm shall not be used to display permanent or temporary advertising, including signage, streamers, pennants, spinners, reflectors, banners, or similar materials. The manufacturers and equipment information, warning, or indication of ownership shall be allowed on any equipment of the solar farm.
(r) A solar farm shall not be constructed until a permit has been approved and issued.
History
(Ord. of 2-3-2022)