146.1. Water. Water mains for both domestic use and fire protection shall be properly connected with the public water system or with an alternate water supply approved by the Jones County Health Department. The lines shall be constructed in such a manner as to serve adequately all lots shown on the subdivision plat. The lines shall be installed in conformance with the technical standards as established by the board of commissioners. 146.2. Sewer. A publicly connected sanitary sewer system shall be installed when the cost of installing such a system does not exceed 150 percent of the cost of installing septic tanks for all lots in the subdivision, and where said system is available from a public agency, subject to regulation by the board of commissioners, or as the result of a contract between that board and another public agency or body. Where lots cannot be economically connected with a sewerage system, they must contain adequate area for the installation of septic tanks and disposal fields approved by the Jones County Health Department. All sewer facilities shall be installed in accordance with the standards of the department of public health of the State of Georgia, and the Jones County Board of Commissioners. 146.3. Gas. When gas mains are connected with the gas distribution system of the unincorporated area of Jones County, the lines shall be installed in such a manner as to serve adequately all lots shown on the subdivision plats. The gas lines shall be constructed in conformance with the technical standards established by the board of commissioners. 146.4. Utility placement schedule. All utilities installed on the right-of-way of subdivision streets will be installed according to the following: For streets with curb and gutter: For open ditch: