Sec. 18-275. Performance and maintenance bonds.

About this text

  • As published by Municode, current through 2026-01-16
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Application procedure.

(1) Applications for land development permits shall be filed with the zoning director.

(2) Permit applications shall include the items set forth in section 18-271 above (two copies of the stormwater management plan and the inspection maintenance agreement, if applicable, shall be included).

(3) The zoning director shall inform the applicant whether the application, stormwater management plan and inspection and maintenance agreement are approved or disapproved.

(4) If either the permit application, stormwater management plan or inspection and maintenance agreement are disapproved, the zoning director shall notify the applicant of such fact in writing. The applicant may then revise any item not meeting the requirements hereof and resubmit the same, in which event subsection (3) above and this subsection shall apply to such resubmittal.

(5) Upon a finding by the zoning director that the permit application, stormwater management plan and inspection and maintenance agreement, if applicable, meet the requirements of this article, the zoning director may issue a permit for the land development project, provided all other legal requirements for the issuance of such permit have been met.

(6) Notwithstanding the issuance of the permit, in conducting the land development project, the applicant or other responsible person shall be subject to the following requirements:

a. The applicant shall comply with all applicable requirements of the approved plan and this article and shall certify that all land clearing, construction, land development and drainage will be done according to the approved plan;

b. The land development project shall be conducted only within the area specified in the approved plan;

c. The zoning director or any county employee designated by the zoning director shall be allowed to conduct periodic inspections of the project;

d. No changes may be made to an approved plan without review and written approval by the zoning director; and,

e. Upon completion of the project, the applicant or other responsible person shall submit the engineer's report and certificate and as-built plans required by section 18-312.

(b) Application review fees. The fee for review of any stormwater management application shall be based on the fee structure established by Jones County and shall be made prior to the issuance of any building permit for the development.

(c) Modifications for off-site facilities. The stormwater management plan for each land development project shall provide for stormwater management measures located on the site of the project, unless provisions are made to manage stormwater by an off-site or regional facility.

The off-site or regional facility must be located on property legally dedicated for the purpose, must be designed and adequately sized to provide a level of stormwater quantity and quality control that is equal to or greater than that which would be afforded by on-site practices and there must be a legally-obligated entity responsible for long-term operation and maintenance of the off-site or regional stormwater facility. In addition, on-site measures shall be implemented, where necessary, to protect upstream and downstream properties and drainage channels from the site to the off-site facility.

A stormwater management plan must be submitted to the zoning director which shows the adequacy of the off-site or regional facility.

To be eligible for a modification, the applicant must demonstrate to the satisfaction of the zoning director that the use of an off-site or regional facility will not result in the following impacts to upstream or downstream areas:

(1) Increased threat of flood damage to public health, life, and property;

(2) Deterioration of existing culverts, bridges, dams, and other structures;

(3) Accelerated streambank or streambed erosion or siltation;

(4) Degradation of in-stream biological functions or habitat; or

(5) Water quality impairment in violation of state water quality standards, and/or violation of any state or federal regulations.

History

The history line the source prints at the end of the section.

(Ord. No. 200612-1o, § 3.5, 12-5-2006)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:jones-county/code/18-275@2026-01-16-ad9509095d

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Jones County Code of Ordinances, Sec. 18-275. Performance and maintenance bonds | Georgia Commons