In lieu of requiring the completion of all required improvements prior to the acceptance of a final plat, the governing authority may, at its discretion, accept a bond or guarantee from the subdivider, whereby the subdivider shall guarantee to complete all required improvements by this Code or otherwise specified by the county engineer/designee or his designated representative, to the satisfaction of the local governing authority. Remaining primary improvements must be completed within six months from the date of final plat approval by the governing authority. Remaining secondary improvements must be completed within two years from the date of final plat approval by the governing authority. The amount of the guarantee shall be 115 percent of the construction cost of the required improvements. The developer's engineer shall estimate cost for construction or a copy of the construction contract shall be provided. The amount of the guarantee must be approved as adequate to the local governing authority or representative. The time of guarantee shall be 12 months and shall automatically renew until released by the governing authority/designee. The guarantee shall be in the form of one of the following alternatives: (1) Performance bond. (2) Irrevocable letter of credit and its accompanying agreement. (3) Cash bond and escrow agreement. (4) Such other security arrangements as may be approved by the governing authority's attorney.