(a) Permits shall be issued or denied as soon as practicable, but in any event, not later than 45 days after receipt by the local issuing authority of a completed application, providing variances and bonding are obtained, where necessary. (b) No permit shall be issued by the local issuing authority unless the erosion and sedimentation control plan has been approved by the district, and the local issuing authority has affirmatively determined that the plan is in compliance with this article, any variances required by section 18-48(15) and (16) are obtained, bonding requirements, if necessary, as per section 18-104(g) are met, and all provisions and rules and regulations in effect within the jurisdictional boundaries of the local issuing authority are met. If the permit is denied, the reason for denial shall be furnished to the applicant. (c) If the tract is to be developed in phases, then a separate permit shall be required for each phase. (d) The permit may be suspended, revoked, or modified by the local issuing authority, as to all or any portion of the land affected by the plan, upon finding that the holder or his successor in the title is not in compliance with the approved erosion and sedimentation control plan, or that the holder or his successor in title is in violation of this article. A holder of a permit shall notify any successor in title to him as to all or any portion of the land affected by the approved plan, of the conditions contained in the permit.