Macon County · Code of Ordinances
Part II - CODE OF ORDINANCES / Chapter 10 - BUILDINGS AND BUILDING REGULATIONS
Sec. 10-16. Inspections.
About this text
- As published by Municode, current through 2020-08-20
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Generally. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. Approval as a result of an inspection shall not be construed to be an approval of a violation of the provisions of this chapter or of other applicable provisions of the code. Inspections presuming to give authority to violate or cancel the provisions of this chapter or of other provisions of the code shall not be valid. It shall be the duty of the permit applicant to cause the work to remain accessible and exposed for inspection purposes. Neither the building official not the county shall be liable for any expense entailed in the removal of any material required to allow inspection.
(b) Preliminary inspection. Before issuing a permit, the building official is authorized to examine buildings, structures and sites for which an application has been filed.
(c) Required inspections. The building official, upon notification, shall make the inspections set forth as follows:
(1) Building.
a. Foundation and slab inspection. To be made after trenches are excavated, forms are erected, and reinforcement is installed but before concrete is put in place. The appropriate silt and erosion control measures must be in place and functional.
b. Dam proofing inspection. To be made prior to backfill of crawl space or basement foundation walls.
c. Pre-cladding/frame inspection. To be made after the roof, wall bracing, windows, doors and moisture barrier are installed and prior to placement of exterior cladding. Rough inspections on trades need not be complete for pre-cladding inspection.
d. Frame/insulation inspection. To be made after wiring, piping, chimneys, duct and vents to be concealed are in place and all rough inspections approved, fire blocking is in place and the insulation in walls and inaccessible ceilings is installed. Insulation values must meet documents submitted with permit application.
e. Final inspection. To be made after the building or structure is completed in compliance with this Code prior to issuance of the certificate of occupancy.
(2) Electrical.
a. Underground and slab inspection. To be made after trenches or ditches are excavated, forms are erected, and conduit or cable are installed, and before any backfill or concrete is put in place.
b. Rough-in inspection. To be made after the roof, framing, fire blocking, bracing, and wiring are in place and prior to the installation of insulation and wall and ceiling membranes.
c. Final inspection. To be made after the building or structure is complete, all required electrical outlets, switches and fixtures are in place and properly connected or protected, and the building or structure is ready for occupancy.
(3) Plumbing.
a. Underground and slab inspection. To be made after trenches or ditches are excavated, forms are erected, piping installed and before any backfill or concrete is put in place. The appropriate silt and erosion control measures must be in place and functional.
b. Rough-in inspection. To be made after the roof, framing, fire blocking and bracing are in place and all water, soil, waste and vent piping is complete and prior to the installation of wall and ceiling membranes.
c. Final inspection. To be made after the building is complete, and all plumbing fixtures and appliances are in place and properly connected, and the structure is ready for occupancy.
d. Testing. Plumbing work and systems shall be tested as required in section 312 of the standard plumbing code. Tests shall be made by the permit holder and observed by the building official.
(4) Mechanical.
a. Underground and slab inspection. To be made after trenches or ditches are excavated, forms are erected, underground duct and fuel piping is installed and before any backfill and concrete is put in place.
b. Rough-in inspection. To be made after the roof, framing, fire blocking and bracing are in place and all duct and fuel piping to be concealed are complete and prior to the installation of wall and ceiling membranes.
c. Final inspection. To be made after the building is complete, the mechanical system and appliances are in place and properly connected and the structure is ready for occupancy.
(5) Gas.
a. Rough-in inspection. To be made after all piping authorized by the permit has been installed and before any such piping has been covered and concealed or any fixtures or appliances have been connected.
b. Final piping inspection. To be made after all piping authorized by the permit has been installed, after all portions which are to be covered or concealed by wall and ceiling membranes, plastering, stone or brickwork have been so concealed, and before any fixtures or gas appliances have been connected. Log lighters shall be permitted separately and inspected.
c. Testing. This inspection shall include a gas pressure test.
d. Final inspection. To be made on all new gas work authorized by the permit and such portions of existing systems as may be affected by the new work or any changes, to insure compliance with the requirements of this chapter and to assure that the installation and construction of the gas system is in accordance with reviewed plans.
(d) Residential flood plain inspections. For construction permitted in areas prone to flooding as established by table R301.2(1) of the International Residential Building Code, and by the state department of natural resources upon placement of the lowest floor, including basement, and prior to further vertical construction, the building official shall require submission of a certification of the elevation of the lowest floor, including basement, prepared by a registered professional engineer or land surveyor, as required in section R327 of the International Residential Building Code. No work or alteration can be conducted until this area is determined.
(e) Fire-resistant penetrations. Protection of joints and penetrations in fire-resistancerated assemblies shall not be concealed from view until inspected and approved.
(f) Other inspections. In addition to any other inspections, the building official is authorized to make or require other inspections of any construction work to ascertain compliance with the provisions of this chapter and other applicable provisions of the code that are enforced by the planning and development services department.
(g) Residential fire-resistance-rated construction inspections. Where fire-resistancerated construction is required between dwelling units or due to the location on the property, the building official shall require an inspection of such construction after all lathing and/or wallboard is in place, before any plaster is applied, or before wallboard joints and fasteners are taped and finished.
(h) Inspection agencies. The building official is authorized to request and accept reports of approved inspection agencies, provided such agencies satisfy the requirements of this chapter.
(i) Prequalified inspections. Prequalified alternate registered engineer inspections are allowed as follows:
(1) When it is evident that the county cannot provide an inspection service of construction covered by this chapter within four business days of receiving a valid written request for any inspection, then, in lieu of an inspection by inspections personnel employed by the county, any person, firm, or corporation engaged in a construction project which requires an inspection, shall have the option of retaining, at their own expense, a prequalified alternate registered professional engineer who holds a certificate of registration issued under chapter 15 of title 43 of the Official Code of Georgia and who is not an employee or otherwise affiliated with or financially interested in such person, firm, or corporation, to provide the required inspection. Prequalified alternate registered professional engineers shall conduct inspections in accordance with all applicable provisions of this Code and state law, including, but not limited to, O.C.G.A. § 8-2-26, as amended.
(2) The county shall provide for the prequalification of alternate registered engineers who may perform inspections pursuant to this section. A prequalified alternate registered engineer inspector who personally makes the inspecBUILDINGS AND BUILDING REGULATIONS § 10-16 tion, shall hold, in addition to the certificate registration required under chapter 15 International Code Council/ICC of title 43 of the Official Code of Georgia, a certification that matches the inspector's area of expertise. Prequalified alternate registered engineers may provide inspections in their scope of expertise providing they hold the aforementioned certifications that match their expertise. In lieu of personally holding an international code council certification, a registered engineer may employ technicians who hold the required appropriate international code council certifications to actually make the inspections. These employees shall also be prequalified by the county.
Inspection reports submitted to the county shall contain both the certified technician's signature and the signature and seal of the prequalified alternate registered engineer and their dates of certification.
(3) Prequalified alternate registered engineer inspections and reports shall be accepted only from persons or firms who have been prequalified by the board.
The requirements, procedures, application forms and report forms shall be as adopted by the board. Applications for approval as a prequalified alternate registered engineer inspector may be obtained from the planning and development services department.
(j) Inspections requests. It shall be the duty of the holder of the permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide safe access to and a safe means for inspection of such work for any inspections that are required by this chapter.
(k) Approval required. Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the building official. The building official, upon notification, shall make the requested inspections and shall either indicate the portion of the construction that is satisfactory as completed or shall notify the permit holder or an agent of the permit holder wherein the same fails to comply with this Code. Any portions that do not comply shall be corrected and such portion shall not be covered on concealed until authorized by the building official.
(l) Reinspection fee. Reinspection fees shall be required in accordance with the fee schedule as adopted by the governing authority when work performed is required to be reinspected due to the following reasons:
(1) The reinspection is not approved due to a failure to correct a previously noted code violation on a prior inspection;
(2) The job is not ready for inspection when an inspection is requested and performed;
(3) The building or structure is not accessible and inspection cannot be performed;
(4) Work to be inspected has been covered or concealed and proper inspection cannot be performed; or
(5) Prior issuance of a stop work order requires reinspection.
(m) Right of entry. Inspections required under the provisions of this chapter shall be made by the building official or designee. Upon presentation of proper credentials, the building official or designee may enter the premises between 8:00 a.m. and 7:00 p.m. to perform any duty imposed by this chapter provided that the building official or designee has consent to enter the premises or has obtained and presents an inspection warrant as described in this chapter.
History
(Ord. of 3-1-2011(03), § 1-16)
Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.