Sec. 10-18. Utility service connections.

About this text

  • As published by Municode, current through 2020-08-20
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Connection of service utilities. No person shall make connections from a utility, source of energy, fuel or power to any building or system that is regulated by this chapter for which a permit is required, until approved by the building official.

(b) Permanent electrical service connection. Permanent electrical service connection and meter shall not be authorized until all required final building, plumbing, mechanical, gas, electrical, drainage, vegetation, fire and health inspections have been performed and approved by the appropriate city or state department or official.

(c) Permanent gas service connection. Permanent gas service connection and meter shall not be authorized until the gas supply house line has been tested, inspected and approved and all appliance and equipment connections have been inspected and approved.

(d) Temporary electrical and gas service connections. Temporary electrical and gas service and meter connections may be authorized for a specified period of time when the system has been inspected and found to be safe for the connections and use authorized. Such temporary service connections shall be authorized only for the following reasons:

(1) Testing of appliances and equipment.

(2) Temporary occupancy of the building or structure only for the training of employees or stocking of merchandise.

(3) Single-tenant occupancy buildings and multitenant occupancy buildings for which temporary service connections have been authorized shall not be allowed access by the general public for business activity other than those allowed in subsections (d)(1) and (d)(2) of this section.

(e) Authority to disconnect utility services. The building official shall have the authority to authorize disconnection of utility service to the building, structure or system regulated by this chapter in case of an emergency, where necessary to eliminate an immediate danger to life or property. Where possible, the owner and occupant of the building, structure or service system shall be notified of the decision to disconnect utility service prior to taking such action. If not notified prior to disconnecting, the owner or occupant of the building, structure or service system shall be notified in writing, as soon as practical thereafter.

(f) Connection after order to disconnect. No person shall make connections from any energy, fuel, power supply or water distribution system or supply energy, fuel or water to any equipment regulated by this chapter that has been disconnected or ordered to be disconnected by the building official or the use of which has been ordered to be discontinued by the building official until the building official authorizes the reconnection and use of such equipment.

History

The history line the source prints at the end of the section.

(Ord. of 3-1-2011(03), § 1-18)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:macon-county/code/10-18@2020-08-20-8dd7c949b4

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Macon County Code of Ordinances, Sec. 10-18. Utility service connections | Georgia Commons