Sec. 2-662. Contracts, change orders.

About this text

  • As published by Municode, current through 2020-08-20
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Purpose. Contracts may be used for purchases pursuant to any of the methods provided for herein or for purchases pursuant to any exception provided herein. A contract is appropriate when engaging in construction or when purchasing goods and/or services where a purchase order is not adequate to describe all the terms and conditions of the agreement. The contract establishes the legal working relationship between two parties. It shall specify any applicable terms including, but not limited to, payment, performance, maintenance, guaranties, termination, etc. Change orders are addenda to contracts which authorize additional work or a modified scope of work.

(b) Signing authority.

(1) Contracts which are valued less than $25,000.00.

a. Contracts which are valued less than $25,000.00 may be executed by the county manager as designee for the board. In this event, the department head, finance officer, county attorney, and county manager must sign the appropriate request, each affirming that they have reviewed the contract and agree to the terms provided for therein.

b. Change orders may be executed by the county manager as designee for the board as long as the amended contract value does not exceed $25,000.00.

In this event, the project manager and county manager must sign the appropriate request, each affirming that they have reviewed the contract and agree to the terms provided for therein. If there are any contract language changes, the county attorney must also approve.

c. In the event the change order will result in the value of the contract exceeding $25,000.00, then the change order must be signed by the board.

(2) Contracts which are valued at $50,000.00 or more.

a. Contracts which are valued at $50,000.00 or more must be executed by the board.

b. Change orders up to ten percent of the original contract cost or up to $50,000.00 whichever is less, may be executed by the county manager as designee for the board. In this event, the project manager, finance officer and county manager must sign the appropriate request, each affirming that they have reviewed the contract and agree to the terms provided for therein. If there are any contract language changes, the county attorney must also approve.

c. Change orders greater than ten percent of the original contract cost must be approved by the board.

History

The history line the source prints at the end of the section.

(Ord. of 3-1-2011(01), § VI)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:macon-county/code/2-662@2020-08-20-847533e561

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Macon County Code of Ordinances, Sec. 2-662. Contracts, change orders | Georgia Commons