3.10.4. Automatic approval. Failure of the board
About this text
- As published by Municode, current through 2025-03-04
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
of commissioners to act on the final plat within sixty (60) days after submission thereof shall be deemed to be approval of the plat, and a certificate of final approval shall be issued by the board of commissioners on demand, provided, however,
that the subdivider may waive this requirement and consent to an extension of time.
3.10.5. "As-built" plans when required. After the preparation of the final plat; and before any improvements are accepted for maintenance; and before the subdivider or his agent are released from any bond requirement specified herein, the subdivision review officer shall receive formal written notice that all improvements have been installed as approved within thirty (30) days of completion. In instances where said improveAPPENDIX A—SUBDIVISIONS § 3.10 ments have been installed in such a manner as to
vary from the approved construction plans, a copy of "as-built" construction plans shall be submitted to the subdivision review officer.