3.6.1. When required.

About this text

  • As published by Municode, current through 2025-03-04
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Any subdivision which

involves the construction of a new public or private street, upon approval of a preliminary plat, and prior to the installation of any required

improvements, the subdivider or land developer shall apply for construction plan approval. No application for construction plans shall be accepted for processing nor approved by the subdivision review officer until a preliminary plat, has been approved by the board of commissioners and

the proposed construction plans are found by the subdivision review officer to be in substantial conformity with said approval and any conditions of such approval.

3.6.2. Construction plan application. Construction plans shall be prepared by either a registered Georgia professional land surveyor or a registered

Georgia professional engineer. Application for construction plan approval must be submitted within twelve (12) months of preliminary plat approval.

3.6.3. Approved erosion and sedimentation control plan required. No application for construction plans shall be accepted for processing unless an

erosion and sedimentation control plan that has been approved by the Towaliga Soil and Water Conservation Commission is submitted with the construction plans.

3.6.4. Construction plan review. The construction plan approval process is administrative. The subdivision review officer will distribute construction plans to the road superintendent and the county water department. The subdivision review

officer, and each applicable department, shall check the construction plans for conformance to the rules and regulations set forth in this appendix. The subdivision review officer, road superintendent, and the county water department shall note any findings within ten (10) working days.

3.6.5. Pre-construction conference. After approval of the construction plans and prior to beginning work on the development, the subdivision review officer, road superintendent, and the county water department will hold a pre-construction conference with the developer. The subdivision review officer will establish a time and date for the pre-construction conference and notify the

developer.

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:monroe-county/code/3.6.1@2025-03-04-aa7f241b50