The following performance criteria shall be applicable to all stormwater management plans, unless otherwise provided for in this division:
(1) Water quality. Stormwater runoff generated from a site shall be adequately treated before discharge. It will be presumed that a stormwater management system complies with this requirement if:
a. The system is sized to treat the prescribed water quality treatment volume from the site, as defined in the LDM;
b. Appropriate structural stormwater controls or nonstructural practices are selected, designed, constructed or preserved, and maintained in accordance with the specific criteria in the LDM; and
c. Runoff from hotspot land uses and activities identified in the LDM are adequately treated and addressed through the use of appropriate structural stormwater controls, nonstructural practices and pollution prevention practices.
(2) Stream channel protection. Protection of stream channels from bank and bed erosion and degradation shall be provided by using all of the following three approaches:
a. Preservation, restoration and/or reforestation (with native vegetation) of the applicable stream buffer;
b. Twenty-four-hour extended detention storage of the one-year, 24-hour return frequency storm event;
c. Erosion prevention measures such as energy dissipation and velocity control. All design and construction work that is undertaken proximate to stream channels (including the buffer areas) shall be in strict conformance with current local, state and federal regulations.
(3) Flood protection. Flood and public safety protection shall be provided by controlling and safely conveying storm events such that flooding is not exacerbated for the storm events specified in the LDM and in accordance with applicable requirements in chapter 26.
(4) Drainage system guidelines. Stormwater conveyance facilities, which may include, but are not limited to, culverts, stormwater drainage pipes, catch basins, drop inlets, junction boxes, headwalls, gutters, swales, channels, ditches, and energy dissipaters shall be provided when necessary for the protection of public and private properties adjoining project sites. Stormwater conveyance facilities that are designed to carry stormwater runoff from more than one parcel, existing or proposed, shall meet the following requirements:
a. Methods to calculate stormwater flows shall be in accordance with the LDM;
b. All culverts, pipe systems and open channel flow systems shall be sized in accordance with the stormwater management plan using the methods included in the LDM; and
c. Design and construction of stormwater conveyance facilities shall be in accordance with the criteria and specifications found in the LDM.
(5) Dam design guidelines. Any land-disturbing activity that involves a property, which is proposed to contain a dam, shall comply with the provisions of this section.
a. New dams which become subject to the requirements of the Georgia Safe Dams Act and Rules for Dam Safety. Dams proposed to be 25 feet or more in height or proposed to have an impounding capacity of 100 acre-feet or more at maximum water storage elevation shall be subject to the following:
1. If a development is located within the breach zone of a dam, then the dam shall be subject to the requirements of the Georgia Safe Dams Act and Rules for Dam Safety adopted by the state department of natural resources. The developer shall obtain necessary approvals and permits from the environmental protection division of the state department of natural resources for the project and the dam prior to securing a land-disturbance permit from the county. If the development is not located within the breach zone, the developer shall submit construction plans to the county prior to securing a land-disturbance permit from the county.
2. If the developer elects to construct the dam in accordance with the design standards for new dams as contained in the rules for dam safety, then new development shall be permitted within the dam breach zone. However, the dam shall meet the design standards for new dams as contained in the rules for dam safety if development currently exists or is proposed in the dam breach zone.
3. If the developer elects not to construct the new dam to the design standards for new dams as contained in the rules for dam safety, then a dam breach analysis for the dam shall be submitted along with the construction plans prior to securing a landdisturbance permit from the county. The dam breach analysis shall be certified by a professional engineer licensed in the state and approved by the state safe dams program. The design engineer shall utilize the computer models entitled "DAMBRK" or "HEC-RAS" for the dam breach analysis.
4. Should the dam not meet the design standards for dams as contained in the rules for dam safety, then only the following uses and structures shall be permitted within the dam breach zone:
(i) Agriculture which requires no structures for human habitation within the dam breach zone including forestry, livestock raising, and agricultural and forestry access roads.
(ii) Fences.
(iii) Outdoor advertising signs provided they are located no closer than 100 feet from any residence or place of business.
(iv) Roads, driveways and parking areas.
(v) Utility poles, towers, pipelines, water treatment outfalls and facilities, or other similar facilities and structures.
5. For any dam that is proposed not to meet the design for new dams as contained in the rules for dam safety, the developer shall obtain a dam breach easement, recorded with the clerk of superior court, from any off-site property owner where it is proposed for the dam breach zone to extend off the property where the dam is being constructed. The developer shall also cause a dam breach easement to be recorded upon the property being developed.
6. Prior to recording of a final plat or issuance of a certificate of occupancy, as appropriate, an as-built survey must be performed by a professional land surveyor and an as-built design certification must be performed by a professional engineer currently registered in the state. Both certifications must be submitted to the director. The certification shall state that the dam is constructed in accordance with the provisions of this article, as well as the approved construction plans. If the project is for the development of a subdivision, the developer shall also establish a legal entity, acceptable to the county, such as a mandatory homeowners' association (HOA) that will be responsible for the perpetual maintenance of the dam and its impoundment, prior to approval of the final plat.
b. Dams subject to regulation by the county. Dams proposed to be nine feet or more in height, but less than 25 feet in height, in combination with an impounding capacity proposed to be 20 acre-feet or more at maximum water storage elevation, but less than 100 acre-feet, shall be subject to the following:
1. If the developer elects not to construct the dam to the design standards for dams as contained in the rules for dam safety, then a dam breach analysis for the dam shall be submitted to the director with the construction plans prior to securing a landdisturbance permit from the county. The dam breach analysis shall be certified by a professional engineer licensed in the state and approved by the state safe dams program. The design engineer shall utilize the computer models entitled "DAMBRK" or "HEC-RAS" for the dam breach analysis.
2. Should the dam not meet the design standards for dams as contained in the rules for dam safety, then only the following uses and structures shall be permitted within the dam breach zone:
(i) Agriculture which requires no structures for human habitation within the dam breach zone including forestry, livestock raising, and agricultural and forestry access roads.
(ii) Fences.
(iii) Outdoor advertising signs provided they are located no closer than 100-feet from any residence or place of business.
(iv) Roads, driveways and parking areas.
(v) Utility poles, towers, pipelines, water treatment outfalls and facilities, or similar facilities and structures.
3. If the developer elects to construct the dam in accordance with the design standards for dams as contained in the rules for dam safety, then new development shall be permitted within the dam breach zone. However, the dam shall meet the design standards for dams as contained in the rules for dam safety if development currently exists or is proposed in the dam breach zone.
4. Construction plans for dams defined herein shall be submitted to the county prior to securing a land-disturbance permit from the county. The plans shall be certified by a professional engineer licensed in the state and approved by the state safe dams program.
5. For any dam that is proposed not to meet the design standards for dams as contained in the rules for dam safety, the developer shall obtain a dam breach easement, recorded with the clerk of superior court, from any off-site property owner where it is proposed for the dam breach zone to extend off the property where the dam is being constructed. The developer shall also cause a dam breach easement to be recorded upon the property being developed.
6. Prior to recording of a final plat or issuance of a certificate of occupancy, as appropriate, the required as-built certifications, as stated herein, shall be submitted to the director.
c. Existing dams. Existing dams that are located on a project site and will remain after construction is complete, shall comply with the provisions of this division and all referenced divisions as if they were new dams.
d. Existing category II dams. When an existing category II dam would be reclassified to a category I dam because of a proposed development downstream of the dam, the following shall be provided by the developer for review by the state safe dams program.
1. Location of the category II dam and the proposed development;
2. A surveyed cross-section of the stream valley at the location of the proposed development including finished floor elevations; and
3. A dam breach analysis using the "DAMBRK" or "HEC-RAS" computer model to establish the height of the flood wave in the downstream floodplain. The "DAMBRK" or "HEC-RAS" modeling shall be completed in accordance with the safe dams program by a qualified registered engineer licensed in the state and approved by the state safe dams program.
History
(Ord. No. O-090506, § 400-060, 9-5-2006)
Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.