Part - CODE OF ORDINANCES / Chapter 66 - UTILITIES / Article 12 - PROCEDURES AND PERMITS
Sec. 1203.05. Multi-family and nonresidential projects.
About this text
- As published by Municode, current through 2026-04-07
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
a. Project Approval is granted by the Planning Director upon review and approval of a Preliminary Site Plan for the project by the Development Review Committee. Where no subdivision or condominium is proposed, the review and approval of a Preliminary Site Plan is optional unless required by the Planning Director.
b. A Development Permit is issued by the Planning Department based on review and approval by all affected departments and agencies of development plans for construction of the project.
c. A Building Permit is issued by the Planning Department based on review and approval of architectural plans. Buildings falling under the authority of the State Fire Marshal shall be approved by the Fire Marshal prior to issuance of the building permit.
d. Driveway and sign permits are issued by the appropriate departments.
e. Receipt by the Public Works Director (for streets and drainage), the Water Resources Director (for water and sewer), and the Planning and Code Enforcement Director (for buildings and parking) of accurate surveys of the as-built condition of all public and required improvements is required in order to authorize issuance of a Certificate of Occupancy.
f. Occupancy of the building is authorized by the Planning Director based on final inspection and issuance of a Certificate of Occupancy.
History
(Res. of 2-4-2025(1), Exh. A)