Part - CODE OF ORDINANCES / Chapter 66 - UTILITIES / Article 12 - PROCEDURES AND PERMITS / Division IV - OTHER PERMITS
Sec. 1223.07. Duration of permit validity.
About this text
- As published by Municode, current through 2026-04-07
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
a. If construction described in the building permit or development permit has not commenced within 12 months from the date of issuance, the permit shall expire.
b. If construction described in the building permit or development permit is suspended or abandoned after work has commenced, the permit shall expire twelve months after the date that work ceased.
c. Written notice of pending expiration of the building permit or development permit may be issued by the Planning Director.