a. All stream buffer areas shall be maintained with appropriate indigenous plant species for the maintenance of groundcover and limitation of erosion. Undisturbed natural vegetation is the preferred, optimum state of a stream buffer. In the alternate, careful reestablishment of indigenous vegetation and ground cover is required.

b. No construction, grading, clearing, grubbing, excavating, filling, or other land disturbing activity shall be permitted within the stream buffer. As an exception to this rule, the following limited uses may be established within the stream buffer provided that: land disturbance and impact in the stream buffer is minimized to the greatest extent possible;

proper soil erosion and sedimentation control is established and maintained; and the disturbed area is stabilized and appropriately revegetated as soon as possible following the completion of approved work within the stream buffer.

(1) Sanitary sewer lines may be located along and across stream buffers if it is determined by the Planning Director that no reasonable design alternative exists.

(2) Other utility lines may cross stream buffers, when it is determined by the utility provider and the Planning Director that no reasonable design alternative exists.

(3) Private driveways and public roads may cross stream buffers as near as possible to 90 degrees when necessary and as approved by Oconee County in the subdivision or development review process.

(4) Recreational amenities (such as trails, wildlife observation stands, and other low impact uses) when approved by Oconee County as an element of a development plan.

(5) Trimming and thinning allowed under Sec. 905.02 shall be limited as follows:

Cutting and clearing (with hand-held tools) of low-lying shrubs and underbrush, live trees less than 1-inch in caliper measured at a point 4.5 feet above grade, and dead trees, provided the stumps and root structure of trees are left in place to ensure minimal soil erosion potential.

(6) Stormwater detention facilities within a natural resources easement required under Sec. 928.01, subject to all State and federal regulations having been met, as evidenced by appropriate written approvals or permits issued by such agencies, and subject to written approval and acceptance by the proposed holder of the natural resources easement. Such facilities are not allowed to be located within a conservation easement required under said Sec. 928.01.

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:oconee-county/code/905.03@2026-04-07-ca739b9a4c

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.