Sec. 18-73. Certificates.

About this text

  • As published by Municode, current through 2025-12-09
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Building occupancy. A new building shall not be occupied or a change made in the occupancy, nature or use of a building or a part of a building until after the county building official has issued a certificate of occupancy. Such certificate shall not be issued until all required electrical, gas, mechanical, plumbing and fire protection systems have been inspected for compliance with the technical codes and other applicable laws and ordinances and released by the county building official.

(b) Issuing certificate of occupancy. Upon satisfactory completion of construction of a building or structure and installation of electrical, gas, mechanical and plumbing systems in accordance with the technical codes, reviewed plans and specifications, and after the final inspection, the county building official shall issue a certificate of occupancy stating the nature of the occupancy permitted, the number of persons for each floor when limited by law, and the allowable load per square foot for each floor in accordance with the provisions of the technical codes.

(c) Temporary/partial occupancy. A temporary/partial certificate of occupancy may be issued for a portion of a building which may be safely occupied prior to final completion of the building.

(d) Existing buildings. A certificate of occupancy for any existing building may be obtained by applying to the county building official and supplying the information and data necessary to determine compliance with the technical codes for the occupancy intended.

Where necessary, in the opinion of the county building official, two sets of detailed drawings, or a general inspection, or both, may be required. When, upon examination and inspection, it is found that the building conforms to the provisions of the technical codes and other applicable laws and ordinances for such occupancy, a certificate of occupancy shall be issued.

(e) Certificate of completion. Upon satisfactory completion of a building, structure, electrical, gas, mechanical or plumbing system, a certificate of completion may be issued.

This certificate does not grant authority to occupy or connect a building, such as a shell building, prior to the issuance of a certificate of occupancy.

History

The history line the source prints at the end of the section.

(Res. No. 99-14, § 13, 2-9-1999)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:paulding-county/code/18-73@2025-12-09-476c13fc9e

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.