Sec. 2-122. Public works contracts and road construction projects.
About this text
- As published by Municode, current through 2023-11-14
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
- Read by OCR from a scanned page: a character, a name, or a number may be misread.
(a) All public works construction contracts subject to this section entered into by the board of commissioners with private persons or entities shall be in writing and on file and available for public inspection in the office of the board of commissioners.
(b) (1) Prior to entering into a public works construction contract other than those exempted by 2-122(g), the board of commissioners shall publicly advertise the contract opportunity. Such notice shall be posted conspicuously in the office of the board of commissioners and shall be advertised in the legal organ. Roads construction projects must be procured in accordance with O.C.G.A. § 34. All roads construction projects exempt from O.C.G.A. § 34 shall meet the requirements of this section.
(2) Contract opportunities that will be awarded by competitive sealed bids shall have plans and specifications available on the first day of the advertisement and shall be open to inspection by the public. The plans and specifications shall indicate if the project will be awarded by base bid or base bid plus selected alternates, and:
a. A statement listing whether all anticipated federal, state, or local permits required for the project have been obtained or an indication of the status of the application for each such permit including when it is expected to be obtained;
and
b. A statement listing whether all anticipated rights of way and easements required for the project have been obtained or an indication of the status as to when each such rights of way or easements are expected to be obtained.
(3) Contract opportunities that will be awarded by competitive sealed proposals shall be publicly advertised with a request for proposals which request shall include conceptual program information in the request for proposals describing the requested services in a level of detail appropriate to the project delivery method selected for the project.
(4) Public works construction projects must be procured in accordance with O.C.G.A § 36. Public works construction projects exempt from O.C.G.A § 36 shall meet the requirements of this section.
(5) All required notices of advertisement shall also advise of any mandatory prequalification requirements or pre-bid conferences. Any advertisement which provides notice of a mandatory pre-bid conference or prequalification shall provide reasonable advance notice of said conference or for the submittal of such prequalification information.
(c) All public works construction contracts subject to the requirements of this section which place the bidder or offeror at risk for construction and require labor or building materials in the execution of the contract shall be awarded on the basis of competitive sealed bidding or competitive sealed proposals. The board of commissioners shall have the authority to reject all bids or proposals or any bid or proposal that is nonresponsive or not responsible and to waive technicalities and informalities.
(d) No addenda modifying plans and specifications shall be issued within a period of 72 hours prior to the advertised time for the opening of bids or proposals, excluding Saturdays, Sundays, and legal holidays. However, if the necessity arises to issue an addendum modifying plans and specifications within the 72-hour period prior to the advertised time for the opening of bids or proposals, excluding Saturdays, Sundays, and legal holidays, then the opening of bids or proposals shall be extended at least 72 hours, excluding Saturdays, Sundays, and legal holidays, from the date of the original bid or proposal opening without need to re-advertise.
(e) Any competitive sealed bidding process shall comply with the following requirements:
(1) The board of commissioners shall publicly advertise an invitation for bids;
(2) Bidders shall submit sealed bids based on the criteria set forth in such invitation;
(3) The board of commissioners shall open the bids publicly and evaluate such bids without discussion with the bidders; and
(4) The contract shall be awarded to the lowest responsible and responsive bidder whose bid meets the requirements and criteria set forth in the invitation for bids; provided, however, that if the bid from the lowest responsible and responsive bidder exceeds the funds budgeted for the public works construction contract, the board of commissioners may negotiate with such apparent low bidder to obtain a contract price within the budgeted amount. Such negotiations may include changes in the scope of work and other bid requirements.
(f) Any competitive sealed proposal shall comply with the following requirements:
(1) The board of commissioners shall publicly advertise a request for proposals, which request shall include conceptual program information in the request for proposals describing the requested services in a level of detail appropriate to the project delivery method selected for the project, as well as the relative importance of the evaluation factors;
(2) The board of commissioners shall open all proposals received at the time and place designated in the request for proposals so as to avoid disclosure of contents to competing offerors during the process of negotiations; and
(3) The board of commissioners shall make an award to the responsible and responsive offeror whose proposal is determined in writing to be the most advantageous to the county, taking into consideration the evaluation factors set forth in the request for proposals. The evaluation factors shall be the basis on which the award decision is made. The contract file shall indicate the basis on which the award is made.
(4) Discussions, negotiations, and revisions may be permitted after submission of proposals and prior to award for the purpose of obtaining best and final offers. In accordance with the request for proposals, all responsible offerors found by the board of commissioners to have submitted proposals reasonably susceptible of being selected for award shall be given an opportunity to participate in such discussions, negotiations, and revisions. During the process of discussion, negotiation, and revision, the board of commissioners shall not disclose the contents of proposals to competing offerors.
(g) Exceptions.
(1) The requirements of this section shall not apply to public works construction projects, when the same can be performed at a cost of less than $100,000.00. Public works construction projects shall not be subdivided in an effort to evade the provisions of this section.
(2) This section shall not apply in the event that the board of commissioners contracts with a governmental entity having a correctional institution for the use of inmate labor from such institution and use the inmates in the performance of any public works construction project.
(3) This section shall not apply in the event that the labor used or to be used in a public works construction project is furnished at no expense by the state or federal government or any agency thereof, and the board of commissioners shall have the power and authority to purchase material for such public works construction project and use the labor furnished free to the county.
(4) The requirements of this section shall not apply to public works construction projects necessitated by an emergency; provided, however, that the nature of the emergency shall be described in the minutes of the board of commissioners. Any contract let by the county pursuant to this subsection shall be ratified, as soon as practicable, on the minutes of the board of commissioners, and the nature of the emergency shall be described therein.
(5) The requirements of this section shall not apply to public works construction projects or any portion of a public works construction project self-performed by the board of commissioners. If the board of commissioners contracts with a private person or entity for a portion of such project, the provisions of this section shall apply to any such contract estimated to exceed $100,000.00.
(6) The requirements of this section shall not apply to sole source public works construction contracts.
(h) Bid bond requirements.
(1) Bid bonds shall be required for all public works construction contracts subject to the requirements of this subsection with estimated bids or proposals over $100,000.00.
However, the board of commissioners may require a bid bond for projects with estimated bids or proposals of $100,000.00 or less.
(2) In the case of competitive sealed bids, a bid may not be revoked or withdrawn until 60 days after the time set by the board of commissioners for opening of bids. Upon expiration of this time period, the bid will cease to be valid, unless the bidder provides written notice to the board of commissioners prior to the scheduled expiration date that the bid will be extended for a time period specified by the board of commissioners.
(3) In the case of competitive sealed proposals, the board of commissioners shall advise offerors in the request for proposals of the number of days that offerors will be required to honor their proposals; provided, however, that if an offeror is not selected within 60 days of opening the proposals, any offeror that is determined by the board of commissioners to be unlikely of being selected for contract award shall be released from his or her proposal.
(4) If the board of commissioners requires a bid bond for any public works construction contract, no bid or proposal for a contract with the board of commissioners shall be valid for any purpose unless the contractor shall give a bid bond with good and sufficient surety or sureties approved by the board of commissioners. The bid bond shall be in the amount of not less than five percent of the total amount payable by the terms of the contract.
(5) In lieu of the bid bond provided for in this subsection, the board of commissioners may accept a cashier's check, or cash in the amount of not less than five percent of the total amount payable by the terms of the contract payable to and for the protection of the county.
(6) When the amount of any bid bond required under this subsection does not exceed $750,000.00, the board of commissioners may, in its sole discretion, accept an irrevocable letter of credit issued by a bank or savings and loan association in the amount and in lieu of the bond otherwise required.
(i) Withdrawal of bids for appreciable errors.
(1) As used in this subsection, the term bid includes proposal and the term bidder includes offeror.
(2) A bidder shall be permitted to withdraw a bid from consideration after the bid opening without forfeiture of the bid security if the bidder has made an appreciable error in the calculation of his or her bid and if:
a. Such error in the calculation of his or her bid can be documented by clear and convincing written evidence;
b. Such error can be clearly shown by objective evidence drawn from inspection of the original work papers, documents, or materials used in the preparation of the bid sought to be withdrawn;
c. The bidder serves written notice upon the board of commissioners prior to the award of the contract and not later than 48 hours after the opening of bids, excluding Saturdays, Sundays, and legal holidays;
d. The bid was submitted in good faith and the mistake was due to a calculation or clerical error, an inadvertent omission, or a typographical error as opposed to an error in judgment; and
e. The withdrawal of the bid will not result in undue prejudice to the governmental entity or other bidders by placing them in a materially worse position than they would have occupied if the bid had never been submitted.
(3) In the event that an apparent successful bidder has withdrawn his or her bid as provided in subsection (i)(2), action on the remaining bids should be considered as though the withdrawn bid had not been received. In the event the project is re-let for bids, under no circumstances shall a bidder who has filed a request to withdraw a bid be permitted to resubmit a bid for the work.
(4) No bidder who is permitted to withdraw a bid pursuant to subsection (i)(2) shall for compensation supply any material or labor to, or perform any subcontract or other work agreement for, the person or firm to whom the contract is awarded or otherwise benefit, directly or indirectly, from the performance of the project for which the withdrawn bid was submitted.
(j) Withdrawal of bid or proposals by affiliated corporation.
(1) Affiliated corporation means, with respect to any corporation, any other corporation related thereto:
a. As a parent corporation;
b. As a subsidiary corporation;
c. As a sister corporation;
d. By common ownership or control; or
e. By control of one corporation by the other.
(2) In any case where two or more affiliated corporations bid or propose for a contract under this subsection and any one or more of such affiliated corporations subsequently rescind or revoke their bid or proposal in favor of another such affiliated corporation whose bid or proposal is for a higher amount and the contract is awarded at such higher amount to such other affiliated corporation, then the bid bond, proposal guaranty, or other security otherwise required under this subsection of each affiliated corporation rescinding or revoking its bid or proposal shall be forfeited.
(k) Performance bond requirements.
(1) Performance bonds shall be required for all public works construction contracts subject to the requirements of this subsection with an estimated contract amount greater than $100,000.00; provided however, that the board of commissioners may require a performance bond for public works construction contracts that are estimated at $100,000.00 or less. No public works construction contract requiring a performance bond shall be valid for any purpose unless the contractor shall give such performance bond. The performance bond shall be in the amount of at least the total amount payable by the terms of the contract and shall be increased as the contract amount is increased.
(2) When the amount of the performance bond required under this subsection does not exceed $750,000.00, the board of commissioners may, in its sole discretion, accept an irrevocable letter of credit by a bank or savings and loan association in the amount of and in lieu of the bond otherwise required under this subsection.
(1) Requirement for payment bonds. Payment bonds shall be required for all public works construction contracts subject to the requirements of this subsection with an estimated contract amount greater than $100,000.00; provided, however, that the board of commission-ers may require a payment bond for public works construction contracts that are estimated at $100,000.00 or less. No public works construction contract requiring a payment bond shall be valid for any purpose, unless the contractor shall give such payment bond; provided, however, that, in lieu of such payment bond, the board of commissioners, in its discretion, may accept a cashier's check, certified check, or cash for the use and protection of all subcontractors and all persons supplying labor, materials, machinery, and equipment in the prosecution of work provided in the contract. The payment bond or other security accepted in lieu of a payment bond shall be in the amount of at least the total amount payable by the terms of the initial contract and shall be increased if requested by the board of commission-ers as the contract amount is increased.
History
(Ord. of 10-26-1993, § XI; Amd. of 12-8-2009; Ord. of 5-14-2019(2))