Sec. 14-50. Permit procedures.
About this text
- As published by Municode, current through 2025-01-07
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Application for a development permit shall be made to the county code inspector on forms furnished by the county prior to any development activities, and may include, but not be limited to, the following plans in duplicate drawn to scale showing the nature, location, dimensions, and elevations of the area in question; and existing or proposed structures, fill, storage of materials, drainage facilities and the location of the foregoing. Specifically, the following information is required:
(1) Application stage.
a. Elevation in relation to mean sea level of the proposed lowest floor (including basement) of all buildings;
b. Certificate from a registered professional engineer or architect that the nonresidential floodproofed building will meet the floodproofing criteria in section 14-79(2);
c. Description of the extent to which any watercourse will be altered or relocated as a result of proposed development.
(2) Construction stage. Provide a floor elevation or floodproofing certification after the lowest floor is completed or instances where building is subject to the regulations applicable to coastal high hazard areas, after placement of the horizontal structural members of the lowest floor. Upon placement of the lowest floor, or floodproofing by whatever construction means, or upon placement of the horizontal structural members of the lowest floor, whichever is applicable, it shall be the duty of the permit holder to submit to the county code inspector a certification of the elevation of the lowest floor, floodproofed elevation, or the lowest portion of the horizontal structure members of the lowest floor, whichever is applicable, as built, in relation to mean sea level. Such certification shall be prepared by or under the direct supervision of a registered land surveyor or professional engineer and certified by the same. When floodproofing is utilized for a particular building, said certification shall be prepared by or under direct supervision of a professional engineer or architect and certified by the same. Any work undertaken prior to submission of the certification shall be at the permit holder's risk.
The county code inspector shall review the floor elevation survey data submitted.
Deficiencies detected by such review shall be corrected by the permit holder immediFLOODS § 14-50 ately and prior to further progressive work being permitted to proceed. Failure to submit the survey, or failure to make said corrections required hereby, shall be cause to issue a stop work order for the project.
History
(Code 2005, § 26-62; Ord. of 10-7-1997, art. 4, § B)
Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.