(a) Data centers shall not cause or permit noise exceeding 60 dBA during the hours of 7:00 a.m. to 10:00 p.m. or 50 dBA during the hours of 10:00 p.m. to 7:00 a.m. at the nearest residential building, school, religious institution, hospital, or public park. (b) Prior to certificate of occupancy, written verification must be submitted to the building inspector from a licensed noise control engineer certifying compliance, using Type 1 sound level meters with 15-minute averaging. Costs from this study are the responsibility of the applicant. (c) Additional barriers or mitigation devices may be required the county. (d) Generator testing shall only take place Monday to Friday, during hours between 9:00 a.m. and 5:00 p.m.