Sec. 10-63. Time limitations.

About this text

  • As published by Municode, current through 2025-04-22
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

An application for a permit for any proposed work shall be deemed to have been abandoned 12 months after the date of filing for the permit, unless before then a permit has been issued. One or more extensions of time for periods of not more than 360 days each may be allowed by the administrative officer for the application, provided the extension is requested in writing and justifiable cause is demonstrated.

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:rabun-county/code/10-63@2025-04-22-63b12fe5d4

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.