Sec. 16-285. Water supply watershed; defined.

About this text

  • As published by Municode, current through 2025-04-22
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Watershed areas within Rabun County correspond to the topographical features that delimit the drainage basins of the respective creeks, streams and rivers within the county.

(b) A "water supply watershed" is the portion of a watershed upstream of a governmentally owned public drinking water supply intake.

(1) A "large water supply watershed" is one having a drainage basin of 100 square miles or greater.

(2) A "small water supply watershed" is one having a drainage basin less than 100 square miles.

(c) Large water supply watersheds: The requirements of this section apply to the large water supply watersheds identified by the State of Georgia associated with the Tallulah River and Little Tennessee River.

(d) Small water supply watersheds: The requirements of this section apply to the small water supply watersheds identified by the State of Georgia associated with Mud Creek.

(e) Upon the creation of a large or small water supply watershed in or extending into Rabun County as the result of construction of a governmentally owned public water drinking water supply intake, the rules of the Georgia Department of Natural Resources adopted pursuant to State law shall apply.

(Ord. of 2-25-2014) Sec. 16-286. conservation corridors in water supply watersheds; buffers.

Along all watercourses within a water supply watershed, the conservation corridors shown on the Future Land Use Map shall be shown on all plans and plats and shall be protected by the following:

(1) Within seven miles upstream from a public water supply intake or reservoir:

a. A minimum 100-foot wide undisturbed buffer as measured outwardly and horizontally from the uppermost part of each stream bank; and

b. A minimum setback from the stream buffer of 50 feet for all impervious surfaces, septic tanks and their drainfields.

(2) Beyond seven miles upstream from a public water supply intake or reservoir in a small water supply watershed:

a. A minimum 50-foot wide undisturbed buffer as measured outwardly and horizontally from the uppermost part of each stream bank; and

b. A minimum setback from the stream buffer of 25 feet for all impervious surfaces, septic tanks and their drainfields.

History

The history line the source prints at the end of the section.

(Ord. of 2-25-2014)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:rabun-county/code/16-285@2025-04-22-64b78f1024

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Rabun County Code of Ordinances, Sec. 16-285. Water supply watershed; defined | Georgia Commons