--- title: Rockdale County Code of Ordinances, Sec. 310-36. Stormwater management standards collection: local-codes id: local-code:rockdale-county/code/310-36 cite_as: Rockdale County, Ga., Code of Ordinances § 310-36 canonical_url: https://georgiacommons.org/counties/rockdale/code/310-36 md_url: https://georgiacommons.org/counties/rockdale/code/310-36.md text_url: https://georgiacommons.org/counties/rockdale/code/310-36/text source_url: https://library.municode.com/ga/rockdale_county/codes/code_of_ordinances date: 2026-01-27 status: active jurisdiction: county:rockdale jurisdiction_name: Rockdale County county_fips: "13247" corpus_version: local-codes-rockdale-county-c3e0b855bd42 publisher: Georgia Commons, an independent project of Georgia Civic Data. Not the State of Georgia. Not legal advice. up: https://georgiacommons.org/counties/rockdale/code/~part-ii/~part-b/~title-3/~chapter-310/~article-iii.md previous: https://georgiacommons.org/counties/rockdale/code/310-35.md next: https://georgiacommons.org/counties/rockdale/code/310-37.md index: https://georgiacommons.org/counties/rockdale.md branch: code edition: As published by Municode, current through 2026-01-27 edition_date_kind: current_through source_publisher: Municode version_id: local-code:rockdale-county/code/310-36@2026-01-27-8892ee3a5d --- # Rockdale County Code of Ordinances, Sec. 310-36. Stormwater management standards > As published by Municode, current through 2026-01-27 > The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included. Part of: Part II - CODE OF ORDINANCES / Part B - PLANNING AND DEVELOPMENT / Title 3 - DEVELOPMENT AND PERMITTING / Chapter 310 - STORMWATER MANAGEMENT / Article III - POST-DEVELOPMENT STORMWATER MANAGEMENT Subject to the applicability criteria in section 310-34 and exemptions in section 310-35, the following stormwater management standards apply. Additional details for each standard can be found in the GSMM 2.2.2.2: (a) Design of stormwater management system: The design of the stormwater management system shall be in accordance with the applicable sections of the GSMM as administered by the stormwater director. Any design which proposes a dam shall comply with the Georgia Safe Dams Act and Rules for Dam Safety as applicable. (b) Natural resources inventory: Site reconnaissance and surveying techniques shall be used to complete a thorough assessment of existing natural resources, both terrestrial and aquatic, found on the site. Resources to be identified, mapped, and shown on the stormwater management plan, shall include, at a minimum (as applicable): (i) Topography (minimum of two-foot contours) and steep slopes (i.e., areas with slopes greater than 15 percent), (ii) Natural drainage divides and patterns, (iii) Natural drainage features (e.g., swales, basins, depressional areas), (iv) Natural feature protection and conservation areas such as wetlands, lakes, ponds, floodplains, stream buffers, drinking water wellhead protection areas and river corridors, (v) Predominant soils (including erodible soils and karst areas), and (vi) Existing predominant vegetation including trees, high quality habitat and other existing vegetation. (c) Better site design practices for stormwater management: Stormwater management plans shall preserve the natural drainage and natural treatment systems and reduce the generation of additional stormwater runoff and pollutants to the maximum extent practicable. Additional details can be found in the GSMM 2.3. (d) Stormwater runoff reduction/water quality: Stormwater runoff reduction/water quality shall be provided by using the following: (i) For development with a stormwater management plan submitted before December 1, 2020, the applicant may choose either: (A) runoff reduction or (B) water quality. (ii) For development with a stormwater management plan submitted on or after December 1, 2020, the applicant shall choose: (A) runoff reduction and additional water quality shall not be required. To the extent (A) runoff reduction has been determined to be infeasible for all or a portion of the site using the practicability policy; then (B) water quality shall apply for the remaining runoff from a 1.2 inch rainfall event and must be treated to remove at least 80 percent of the calculated average annual post-development total suspended solids (TSS) load or equivalent as defined in the GSMM. (A) Runoff reduction - The stormwater management system shall be designed to retain the first 1.0 inch of rainfall on the site using runoff reduction methods, to the maximum extent practicable. (B) Water quality - The stormwater management system shall be designed to remove at least 80 percent of the calculated average annual post-development total suspended solids (TSS) load or equivalent as defined in the GSMM for runoff from a 1.2 inch rainfall event. (iii) If a site is determined to be a hotspot as detailed in section 310-34, Rockdale County may require the use of specific or additional components for the stormwater management system to address pollutants of concern generated by that site. (e) Stream channel protection: Stream channel protection shall be provided by using all of the following three approaches: (i) 24-hour extended detention storage of the 1-year, 24-hour return frequency storm event; (ii) Erosion prevention measures, such as energy dissipation and velocity control; and (iii) Preservation of any applicable stream buffer. (f) Overbank flood protection: Downstream overbank flood protection shall be provided by controlling the post-development peak discharge rate to the pre-development rate for the 25-year, 24-hour storm event. (g) Extreme flood protection: Extreme flood protection shall be provided by controlling and/or safely conveying the 100- year, 24-hour storm event such that flooding and other damage are not exacerbated. (h) Downstream analysis: Due to peak flow timing and runoff volume effects, some structural components of the stormwater management system fail to reduce discharge peaks to pre-development levels downstream from the site. A downstream peak flow analysis shall be provided to the point in the watershed downstream of the site or the stormwater management system where the area of the site comprises ten percent of the total drainage area in accordance with GSMM 3.1.9. This is to help ensure that there are minimal downstream impacts from development on the site. The downstream analysis may result in the need to resize structural components of the stormwater management system. (i) Fencing: Permanent fencing shall be provided around all stormwater management measures and systems which: (i) Have a water depth greater than 4.0 feet during the 100-year, 24-hour storm event; (ii) Have an inboard (i.e. Near the water) slope steeper than 3:1; (iii) Have an outboard (i.e. away from the water) slope steeper than 2:1; or (iv) May otherwise pose a threat to public safety, infrastructure, or the environment. The location, type, and configuration of such fencing shall be approved by the stormwater director, and the stormwater director shall have the right to modify or waive these conditions as deemed appropriate. (j) Easements: Permanent easements shall be provided to allow access from public right-of-way to all stormwater management measures and systems, and shall be sufficiently configured and maintained to facilitate future inspection, maintenance, and construction activities. The proposed location, boundary, condition, and ownership of and maintenance responsibility for such easements shall be approved by the stormwater director prior to recording of any associated plat, deed, or agreement. (k) Offsite and regional facilities: In general accordance with GSMM 4.1.5, an offsite facility or regional facility may be utilized for stormwater management when authorized by the stormwater director. Once authorized: (i) Such facility shall be sufficiently designed, constructed, and maintained to satisfy the stormwater management standards of section 310-36 for the proposed site and any other contributing drainage areas; (ii) All areas upstream and downstream of such facility shall not be adversely affected, and shall be protected with additional measures as appropriate; (iii) Appropriate legal documentation (e.g. easements, deeds, contracts) shall be established to allow the site's runoff to be properly conveyed to such facility and managed by such facility in perpetuity; The stormwater director may rescind or modify authorization to use offsite or regional facilities, and may require additional measures, if at any time these provisions or their supporting documents are violated or invalidated. (1) Stormwater management system inspection and maintenance: The components of the stormwater management system that will not be dedicated to and accepted by Rockdale County, including all drainage facilities, best management practices, credited conservation spaces, and conveyance systems, shall have an inspection and maintenance agreement to ensure that they continue to function as designed. All new development and redevelopment sites are to prepare a comprehensive inspection and maintenance agreement for the onsite stormwater management system. This plan shall be written in accordance with the requirements in section 310-45. ## History (Ord. No. 0-2020-17, § 2, 11-10-2020)