Sec. 332-18. Walls.

About this text

  • As published by Municode, current through 2026-01-27
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) No fence (other than subdivision entrance walls, noise abatement walls or walls used as a required buffer between two dissimilar zoning densities) shall be more than eight feet in height or be constructed on public right-of-way or future street right-of-way. If a wall is to be located adjacent to a public road and within the required yard within a zoning district, the wall shall not exceed four feet in height and should not obstruct sight distance for motorists. Should a wall be erected in error within the right-of-way, Rockdale County shall not be responsible for replacing or repairing the nonconforming structure.

(b) When permanent grades are proposed with a resulting slope steeper than one foot vertical for every two feet of horizontal displacement (2:1), an appropriate retaining structure shall be designed by a registered professional engineer to be constructed of reinforced concrete or other masonry materials designed by a registered professional

engineer in compliance with applicable regulations of the U.S. Occupational Safety and Health Administration. An engineered design may be

substituted for the reinforced concrete design, if the specific vendor has a pre-qualified acceptance from the building official. All structural components of the wall shall meet the minimum building codes for the proposed use.

(c) When the necessity for an earth retaining structure is required for a vertical displacement of 30 inches or less, appropriate landscaping timbers, or approval equal, may be employed if no permanent structure is supported by the soil retained by the retaining wall. The use of railroad cross ties or other timber product will be allowed only in these instances as per detail.

(d) All wall designs must demonstrate complete dimensions for line and grade. Wall design will consider foundation drainage and select backfill

material for the proposed conditions.

(e) Walls shall be located in such a fashion as to not encroach upon existing or proposed drainage easements or drainage courses or floodplains to encumber the natural flow of surface runoff of

stormwater. Walls shall be located at a distance from such water courses to allow for anticipated future maintenance of the easement to prevent a safety hazard to maintenance workers or to jeopardize the structural integrity of the wall.

(f) Walls that are not attached to the permitted structure and require a foundation shall be permitted as a free-standing structure and shall be inspected, as prescribed by the permitting procedure. Walls will be inspected for conformance with the approved design. Any deviation from the

approved design will require the engineer ofrecord to submit a certification of the nonconforming structure along with supporting calculations to indicate that the construction is consistent with the initial design parameters. In the event the inspector has not been provided ample opportunity to inspect the structure, the contractor must provide a certification of the construction by the

engineer of record and geotechnical reports for concrete testing for strength and reinforcing steel specifications. Failure to comply with the requirements of this section will require that the remaining work cease and/or removal of non-conformance until the adequacy of structural integrity is demonstrated to the satisfaction of the director.

(g) Retaining walls that are proposed for the purpose of stormwater retention must be designed in such a way that the walls are capable of a hydrostatic load, as measured from the top of

the foundation footing to the highest elevation along the top of the wall. The hydrological design must allow for a free board dimension of one foot and an emergency overflow capacity equal to the allowable peak discharge for the 100-year storm event. The routing calculations should not take into account the existence of the emergency overSupp. No. 8 CD332:30 flow. Place the overflow device above the projected

100-year flood elevation within the detention area.

(h) Any construction that may impact or be within the right-of-way of an existing or proposed water or sanitary sewer easement must be approved by the utility providing service.

(Ord. No. 0-2006-32, §§ 1-3, 11-28-2006; Ord. No.

0-2007-23, § 12, 10-9-2007)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.